contract agreement · K-3
K-3 - Change Order 3 - Rathje Construction - Original Town Phase 3
Page 2 of 5
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 26 Nov, 2024
Change Order No: 3 (THREE)
Agreement Date: 12/14/2023
PROJECT: Original Town Urbanization – Phase 3 HFC #18218.131
OWNER: Tiffin, IA
CONTRACTOR: Rathje Construction Co.
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Remove and replace retaining wall at 330 Summerhays. Lower existing water line at 331 Summerhays. Install wood cellulose fiber mulch for winter stabilization.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $2,134,856.90
CONTRACT with LAST CHANGE ORDER: $2,192,076.79
THIS CHANGE ORDER AMOUNT: $5,750.00
NEW CONTRACT PRICE: $2,197,826.79
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): Days
NEW Completion Date: September 16, 2025
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER:
CONTRACTOR: See Attached
ENGINEER:
Sources
- sharepoint (K-3 - Change Order 3 - Rathje Construction - Original Town Phase 3.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.