K-3 - Change Order 4 - Boomerang - Well 5 Pump, Controls and Watermain
Page 1 of 1
Text from the PDF text layer; check the PDF for anything that matters.January 8, 2025 CHANGE ORDER NO. 4
WELL 5 PUMP, CONTROLS AND WATER MAIN
TIFFIN, IOWA
Change Order No. 4 adjusts the final project cost due to additional costs incurred by the City as
a result of the issues with disinfection of the raw water line that ultimately led to replacement
of the raw water line. The items will be deducted from the final cost and are as follows:
1. Additional cost for water sample delivery and testing. LS $ 2,755.00
2. Additional electrical cost to operate well to provide water
to flush main and obtain samples prior to acceptance. LS $4,036.40
3. Additional cost to provide emergency repairs over standard
rates for well 4 due to unavailability of Well 5. LS $ 5000.00
4. Additional cost for engineering services after original
completion date and identification of issues. LS $12,798.16
Total: $24,589.56
Change Order No. 4 decreases the contract amount by $ 24,589.56 .
BOOMERANG CORP. CITY OF TIFFIN, IOWA
By Keegan Parizek By
Title Project Manager Title
Date 1/8/2025 Date
VEENSTRA & KIMM, INC. ATTEST:
By By
Title Project Engineer Title
Date January 8, 2025 Date
V&K Job No. 5093/1