contract agreement · K-4
K-4 - Pay Estimate 6 - Boomerang - Well 5 Pump, Controls and Watermain
Page 2 of 2
Text from the PDF text layer; check the PDF for anything that matters. SUMMARY
Total Approved Total Completed
Contract Price $ 779,550.00 $ 786,345.46
Approved Change Order (list each) Change Order No. 1 $ 8,052.88 $ 8,052.88
Change Order No. 2 $ 9,081.57 $ 9,081.57
Change Order No. 3 $ 12,557.60 $ 12,557.60
Change Order No. 4 $ (24,589.56) $ (24,589.56)
Revised Contract Price $ 784,652.49 $ 791,447.95
Stored $ -
Total Earned $ 791,447.95
Retainage (5%) $ 16,212.32
Total Earned Less Retainage $ 775,235.63
Total Previously Approved (list each) Pay Estimate No. 1 $ 210,331.14
Pay Estimate No. 2 $ 131,643.40
Pay Estimate No. 3 $ 270,110.93
Pay Estimate No. 4 $ 54,258.85
Pay Estimate No. 5 $ 108,891.31
Total Previously Approved $ 775,235.63
Percent Complete 100% Amount Due This Request $ -
The amount $0.00 is recommended for approval for payment in accordance with the terms of the contract.
Prepared By: Recommended By: Approved By:
Boomerang Corp. Veenstra & Kimm, Inc. Tiffin, Iowa
Signature: Keegan Parizek Signature: Signature:
Name: Keegan Parizek Name: Dave Schechinger Name:
Title: Project Manager Title: Engineer Title:
Date: 1/8/2025 Date: January 8, 2025 Date:
V&K Job No. 5093/1 2 of 2
Sources
- sharepoint (K-4 - Pay Estimate 6 - Boomerang - Well 5 Pump, Controls and Watermain.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.