January 30, 2025
PROJECT UPDATE
Upcoming Infrastructure Description Next Steps/Schedule
Project
The current wastewater treatment facility (WWTF) has a chloride Final Compliance with NPDES
compliance schedule. There is not any wastewater treatment Permit required October 1, 2025.
equipment/processes designed to remove chloride so typically
source control is the only economical means of meeting MSA presented its findings on
Wastewater Treatment
compliance. The existing treatment facility is at about 50% November 1st, 2022. MSA has
Improvements
capacity. However, if the past growth rate continues an expansion prepared a proposed schedule
will be required in the next 5-7 years. for wastewater treatment, water
treatment and water supply
From design to construction the process typically takes 3-4 years. improvement projects.
MSA is preparing a proposal to model the existing sanitary sewer Proposal for modeling services
Systemwide sanitary sewer model system of Tiffin. This will assist in future review of developments to to be created and presented to
determine if existing system has necessary capacity for service. City.
DOT has agreed to continue the existing permit based on the City’s
plan to replace the signals with a permanent installation in 2026.
Deer View Ave & Tall Grass Ave & Scope includes both pedestrian and vehicle accommodations. MSA Begin conceptual review of
Hwy 6 Intersection Improvements is reaching out to the DOT to request a time extension and will intersection/signals.
begin conceptually reviewing the signals and intersection for DOT
approval.
PROJECT UPDATE
Page 3 of 3
Sources
- sharepoint (M-9 - City Engineer Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.