contract agreement · K-5
K-5 - Professional Services Predesign Agreement with DOT - Highway 6 Improvements
Page 7 of 7
Text from the PDF text layer; check the PDF for anything that matters. Exhibit B
COST SUMMARY BASED ON ENGINEER'S OPINION OF PROBABLE COST
US 6 in Tiffin from Grant St. to Park Rd.
Project No. STP-006-7(098)--2C-52
ESTIMATED COST SHARE ESTIMATED COST SHARE
CATEGORY CITY IOWA DOT CITY IOWA DOT TOTAL
% SHARE % SHARE COST COST
Excavation and Removals 33% 67% $155,172.07 $ 315,046.31 $ 470,218.38
Paving 30% 70% $747,879.00 $ 1,704,813.00 $ 2,452,692.00
Drainage (Storm Sewer) 100% 0% $ 866,860.00 $ - $ 866,860.00
Utililties (Water) 100% 0% $ 302,630.00 $ - $ 302,630.00
Traffic Signals 100% 0% $ 300,000.00 $ - $ 300,000.00
Sidewalk (new) 100% 0% $ 280,048.00 $ - $ 280,048.00
Sidewalk (replace - ADA) 0% 100% $ - $ 164,846.58 $ 164,846.58
Extend Culvert 100% 0% $ 135,451.21 $ - $ 135,451.21
Replace Box Culverts 0% 100% $ - $ 669,318.09 $ 669,318.09
Mobilization, Temp. Traffic Control 50% 50% $ 258,860.88 $ 258,860.88 $ 517,721.77
Sub-Total 49% 51% $ 3,046,901.16 $ 3,112,884.86 $ 6,159,786.03
Inflation - 2 years @ 4.5% 49% 51% $ 280,391.08 $ 286,463.23 $ 566,854.31
Miscellaneous and Contingency 48% 52% $ 627,000.00 $ 668,000.00 $ 1,295,000.00
TOTAL PROJECT 49% 51% $ 3,954,292.24 $ 4,067,348.09 $ 8,021,640.34
2025-P-001_Tiffin