contract agreement · K-3
K-3 - Pay Estimate 23 - Final - Portzen Construction - WWTP Phase Two
Page 3 of 4
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th>ITEMS</th>
<th>UNIT</th>
<th>EST QTY</th>
<th>UNIT PRICE</th>
<th>CONTRACTOR'S BID PRICE</th>
<th>Pay Period 23</th>
<th>TOTAL TO DATE</th>
</tr>
<tr>
<td>GENERAL REQUIREMENTS</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Bonds</td>
<td>LS</td>
<td>1.00</td>
<td>$54,863.00</td>
<td>$54,863.00</td>
<td>$ - </td>
<td>1,000 $44,863.00</td>
</tr>
<tr>
<td>Negotiation</td>
<td>LS</td>
<td>1.00</td>
<td>$1,500.00</td>
<td>$1,500.00</td>
<td>$ - </td>
<td>1,000 $1,500.00</td>
</tr>
<tr>
<td>General conditions</td>
<td>LS</td>
<td>1.00</td>
<td>$184,182.79</td>
<td>$184,182.79</td>
<td>0.01 $1,841.83</td>
<td>1,000 $184,182.79</td>
</tr>
<tr>
<td>Project Superintendent</td>
<td>LS</td>
<td>1.00</td>
<td>$94,000.00</td>
<td>$94,000.00</td>
<td>0.01 $940.00</td>
<td>1,000 $94,000.00</td>
</tr>
<tr>
<td>Project manager</td>
<td>LS</td>
<td>1.00</td>
<td>$62,400.00</td>
<td>$62,400.00</td>
<td>0.01 $624.00</td>
<td>1,000 $62,400.00</td>
</tr>
<tr>
<td>Contractor's Fence</td>
<td>LS</td>
<td>1.00</td>
<td>$2,500.00</td>
<td>$2,500.00</td>
<td>0.01 $25.00</td>
<td>1,000 $2,500.00</td>
</tr>
<tr>
<td>Port-a-potty rental</td>
<td>LS</td>
<td>1.00</td>
<td>$2,250.00</td>
<td>$2,250.00</td>
<td>0.01 $22.50</td>
<td>1,000 $2,250.00</td>
</tr>
<tr>
<td>Job trailer</td>
<td>LS</td>
<td>1.00</td>
<td>$9,750.00</td>
<td>$9,750.00</td>
<td>0.01 $97.50</td>
<td>1,000 $9,750.00</td>
</tr>
<tr>
<td>Setup / Tear Down</td>
<td>LS</td>
<td>1.00</td>
<td>$2,000.00</td>
<td>$2,000.00</td>
<td>0.01 $20.00</td>
<td>1,000 $2,000.00</td>
</tr>
<tr>
<td>Signs</td>
<td>LS</td>
<td>1.00</td>
<td>$2,500.00</td>
<td>$2,500.00</td>
<td>0.01 $25.00</td>
<td>1,000 $2,500.00</td>
</tr>
<tr>
<td>Demolition</td>
<td>LS</td>
<td>1.00</td>
<td>$6,000.00</td>
<td>$6,000.00</td>
<td>0.01 $60.00</td>
<td>1,000 $6,000.00</td>
</tr>
<tr>
<td>Erosion Control</td>
<td>LS</td>
<td>1.00</td>
<td>$9,542.00</td>
<td>$9,542.00</td>
<td>0.10 $954.20</td>
<td>1,000 $9,542.00</td>
</tr>
<tr>
<td>Temporary Heat</td>
<td>LS</td>
<td>1.00</td>
<td>$2,500.00</td>
<td>$2,500.00</td>
<td>0.01 $25.00</td>
<td>1,000 $2,500.00</td>
</tr>
<tr>
<td>Temporary Enclosures</td>
<td>LS</td>
<td>1.00</td>
<td>$5,500.00</td>
<td>$5,500.00</td>
<td>0.01 $55.00</td>
<td>1,000 $5,500.00</td>
</tr>
<tr>
<td>Safety</td>
<td>LS</td>
<td>1.00</td>
<td>$2,500.00</td>
<td>$2,500.00</td>
<td>0.01 $25.00</td>
<td>1,000 $2,500.00</td>
</tr>
<tr>
<td>Daily Cleaning</td>
<td>LS</td>
<td>1.00</td>
<td>$31,050.00</td>
<td>$31,050.00</td>
<td>0.01 $310.50</td>
<td>1,000 $31,050.00</td>
</tr>
<tr>
<td>Pumps</td>
<td>LS</td>
<td>1.00</td>
<td>$2,000.00</td>
<td>$2,000.00</td>
<td>0.05 $100.00</td>
<td>1,000 $2,000.00</td>
</tr>
<tr>
<td>Allowances (by unit price)</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Sludge Removal (50 dry tons)</td>
<td>DT</td>
<td>50.00</td>
<td>$142.30</td>
<td>$71,155.00</td>
<td>$ - </td>
<td>313,200 $56,664.00</td>
</tr>
<tr>
<td>Urban Seeding (2.23 acres)</td>
<td>ACRES</td>
<td>2.23</td>
<td>$15,176.00</td>
<td>$11,486.10</td>
<td>1.80 $2,067.77</td>
<td>1,800 $9,211.37</td>
</tr>
<tr>
<td>Soil Stabilization (2.23 tons)</td>
<td>TONS</td>
<td>700.00</td>
<td>$36,000.00</td>
<td>$19,200.00</td>
<td>818.76 $15,793.96</td>
<td>17,193 $18,760.12</td>
</tr>
<tr>
<td>Stabilization Material (700 tons)</td>
<td>TONS</td>
<td>700.00</td>
<td>$36,000.00</td>
<td>$19,200.00</td>
<td>818.76 $15,793.96</td>
<td>17,193 $18,760.12</td>
</tr>
<tr>
<td>SITE WORK</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Dewatering</td>
<td>LS</td>
<td>1.00</td>
<td>$5,000.00</td>
<td>$5,000.00</td>
<td>0.01 $50.00</td>
<td>1,000 $5,000.00</td>
</tr>
<tr>
<td>Building Demolition</td>
<td>LS</td>
<td>1.00</td>
<td>$12,000.00</td>
<td>$12,000.00</td>
<td>0.01 $120.00</td>
<td>1,000 $12,000.00</td>
</tr>
<tr>
<td>Construction Roads</td>
<td>LS</td>
<td>1.00</td>
<td>$12,000.00</td>
<td>$12,000.00</td>
<td>0.01 $120.00</td>
<td>1,000 $12,000.00</td>
</tr>
<tr>
<td>Selective Demolition</td>
<td>LS</td>
<td>1.00</td>
<td>$15,000.00</td>
<td>$15,000.00</td>
<td>0.01 $150.00</td>
<td>1,000 $15,000.00</td>
</tr>
<tr>
<td>Cleaning Tank A&B</td>
<td>LS</td>
<td>1.00</td>
<td>$15,000.00</td>
<td>$15,000.00</td>
<td>0.01 $150.00</td>
<td>1,000 $15,000.00</td>
</tr>
<tr>
<td>Backfill Treatment Building & Tanks</td>
<td>LS</td>
<td>1.00</td>
<td>$49,875.00</td>
<td>$49,875.00</td>
<td>0.01 $498.75</td>
<td>1,000 $49,875.00</td>
</tr>
<tr>
<td>Site Utilities</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Storm</td>
<td>LS</td>
<td>1.00</td>
<td>$26,800.00</td>
<td>$26,800.00</td>
<td>0.01 $268.00</td>
<td>1,000 $26,800.00</td>
</tr>
<tr>
<td>Sanitary</td>
<td>LS</td>
<td>1.00</td>
<td>$38,400.00</td>
<td>$38,400.00</td>
<td>0.01 $384.00</td>
<td>1,000 $38,400.00</td>
</tr>
<tr>
<td>Site Fencing</td>
<td>LS</td>
<td>1.00</td>
<td>$16,535.00</td>
<td>$16,535.00</td>
<td>0.01 $165.35</td>
<td>1,000 $16,535.00</td>
</tr>
<tr>
<td>Site Paving</td>
<td>LS</td>
<td>1.00</td>
<td>$19,600.00</td>
<td>$19,600.00</td>
<td>0.01 $196.00</td>
<td>1,000 $19,600.00</td>
</tr>
<tr>
<td>Chainlink Fence</td>
<td>LS</td>
<td>1.00</td>
<td>$35,900.00</td>
<td>$35,900.00</td>
<td>0.01 $359.00</td>
<td>1,000 $35,900.00</td>
</tr>
<tr>
<td>Concrete</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Materials</td>
<td>LS</td>
<td>1.00</td>
<td>$139,065.00</td>
<td>$139,065.00</td>
<td>0.01 $139.07</td>
<td>1,000 $139,065.00</td>
</tr>
<tr>
<td>Labor</td>
<td>LS</td>
<td>1.00</td>
<td>$109,200.00</td>
<td>$109,200.00</td>
<td>0.01 $109.20</td>
<td>1,000 $109,200.00</td>
</tr>
<tr>
<td>UV Building</td>
<td>LS</td>
<td>1.00</td>
<td>$45,000.00</td>
<td>$45,000.00</td>
<td>0.01 $450.00</td>
<td>1,000 $45,000.00</td>
</tr>
<tr>
<td>Therm Building</td>
<td>LS</td>
<td>1.00</td>
<td>$45,000.00</td>
<td>$45,000.00</td>
<td>0.01 $450.00</td>
<td>1,000 $45,000.00</td>
</tr>
<tr>
<td>Tank C&D</td>
<td>LS</td>
<td>1.00</td>
<td>$570,000.00</td>
<td>$570,000.00</td>
<td>0.01 $5,700.00</td>
<td>1,000 $570,000.00</td>
</tr>
<tr>
<td>Sludge Building</td>
<td>LS</td>
<td>1.00</td>
<td>$8,000.00</td>
<td>$8,000.00</td>
<td>0.01 $80.00</td>
<td>1,000 $8,000.00</td>
</tr>
<tr>
<td>Masonry Labor</td>
<td>LS</td>
<td>1.00</td>
<td>$66,374.00</td>
<td>$66,374.00</td>
<td>0.01 $663.74</td>
<td>1,000 $66,374.00</td>
</tr>
<tr>
<td>Masonry Material</td>
<td>LS</td>
<td>1.00</td>
<td>$39,854.00</td>
<td>$39,854.00</td>
<td>0.01 $398.54</td>
<td>1,000 $39,854.00</td>
</tr>
<tr>
<td>Metals</td>
<td>LS</td>
<td>1.00</td>
<td>$38,147.00</td>
<td>$38,147.00</td>
<td>0.01 $381.47</td>
<td>1,000 $38,147.00</td>
</tr>
<tr>
<td>FPF Grating</td>
<td>LS</td>
<td>1.00</td>
<td>$2,000.00</td>
<td>$2,000.00</td>
<td>0.01 $20.00</td>
<td>1,000 $2,000.00</td>
</tr>
<tr>
<td>Materials</td>
<td>LS</td>
<td>1.00</td>
<td>$3,000.00</td>
<td>$3,000.00</td>
<td>0.01 $30.00</td>
<td>1,000 $3,000.00</td>
</tr>
<tr>
<td>Labor to Install</td>
<td>LS</td>
<td>1.00</td>
<td>$2,000.00</td>
<td>$2,000.00</td>
<td>0.01 $20.00</td>
<td>1,000 $2,000.00</td>
</tr>
<tr>
<td>Carpentry</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Roof Carpentry</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Material</td>
<td>LS</td>
<td>1.00</td>
<td>$21,000.00</td>
<td>$21,000.00</td>
<td>0.01 $210.00</td>
<td>1,000 $21,000.00</td>
</tr>
<tr>
<td>Labor</td>
<td>LS</td>
<td>1.00</td>
<td>$38,000.00</td>
<td>$38,000.00</td>
<td>0.01 $380.00</td>
<td>1,000 $38,000.00</td>
</tr>
<tr>
<td>Wood Trusses</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Material</td>
<td>LS</td>
<td>1.00</td>
<td>$5,500.00</td>
<td>$5,500.00</td>
<td>0.01 $55.00</td>
<td>1,000 $5,500.00</td>
</tr>
<tr>
<td>Labor</td>
<td>LS</td>
<td>1.00</td>
<td>$11,280.00</td>
<td>$11,280.00</td>
<td>0.01 $112.80</td>
<td>1,000 $11,280.00</td>
</tr>
<tr>
<td>Carpetwork & Taps</td>
<td>LS</td>
<td>1.00</td>
<td>$4,150.00</td>
<td>$4,150.00</td>
<td>0.01 $41.50</td>
<td>1,000 $4,150.00</td>
</tr>
<tr>
<td>Thermal & Moisture</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Rigid Insulation</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Material</td>
<td>LS</td>
<td>1.00</td>
<td>$2,000.00</td>
<td>$2,000.00</td>
<td>0.01 $200.00</td>
<td>1,000 $2,000.00</td>
</tr>
<tr>
<td>Labor</td>
<td>LS</td>
<td>1.00</td>
<td>$2,000.00</td>
<td>$2,000.00</td>
<td>0.01 $200.00</td>
<td>1,000 $2,000.00</td>
</tr>
<tr>
<td>Attic Insulation</td>
<td>LS</td>
<td>1.00</td>
<td>$5,888.00</td>
<td>$5,888.00</td>
<td>0.01 $58.88</td>
<td>1,000 $5,888.00</td>
</tr>
<tr>
<td>Roofing</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>UV Building - material</td>
<td>LS</td>
<td>1.00</td>
<td>$6,500.00</td>
<td>$6,500.00</td>
<td>0.01 $65.00</td>
<td>1,000 $6,500.00</td>
</tr>
<tr>
<td>UV Building - labor</td>
<td>LS</td>
<td>1.00</td>
<td>$4,800.00</td>
<td>$4,800.00</td>
<td>0.01 $480.00</td>
<td>1,000 $4,800.00</td>
</tr>
<tr>
<td>Treatment Bldg - material</td>
<td>LS</td>
<td>1.00</td>
<td>$35,310.00</td>
<td>$35,310.00</td>
<td>0.01 $353.10</td>
<td>1,000 $35,310.00</td>
</tr>
<tr>
<td>Treatment Bldg - labor</td>
<td>LS</td>
<td>1.00</td>
<td>$19,800.00</td>
<td>$19,800.00</td>
<td>0.01 $198.00</td>
<td>1,000 $19,800.00</td>
</tr>
<tr>
<td>Specialties</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Fiberlite Plywood</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Materials</td>
<td>LS</td>
<td>1.00</td>
<td>$9,700.00</td>
<td>$9,700.00</td>
<td>0.01 $97.00</td>
<td>1,000 $9,700.00</td>
</tr>
<tr>
<td>Labor to Install</td>
<td>LS</td>
<td>1.00</td>
<td>$11,730.00</td>
<td>$11,730.00</td>
<td>0.01 $117.30</td>
<td>1,000 $11,730.00</td>
</tr>
<tr>
<td>Piping</td>
<td>LS</td>
<td>1.00</td>
<td>$36,335.00</td>
<td>$36,335.00</td>
<td>0.01 $363.35</td>
<td>1,000 $36,335.00</td>
</tr>
<tr>
<td>Specialties</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Materials</td>
<td>LS</td>
<td>1.00</td>
<td>$300.00</td>
<td>$300.00</td>
<td>0.01 $30.00</td>
<td>1,000 $300.00</td>
</tr>
<tr>
<td>Labor to Install</td>
<td>LS</td>
<td>1.00</td>
<td>$250.00</td>
<td>$250.00</td>
<td>0.01 $25.00</td>
<td>1,000 $250.00</td>
</tr>
<tr>
<td>Summerside Wastewater Pumps</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Materials</td>
<td>LS</td>
<td>1.00</td>
<td>$21,400.00</td>
<td>$21,400.00</td>
<td>0.01 $214.00</td>
<td>1,000 $21,400.00</td>
</tr>
<tr>
<td>Labor to Install</td>
<td>LS</td>
<td>1.00</td>
<td>$2,330.00</td>
<td>$2,330.00</td>
<td>0.01 $23.30</td>
<td>1,000 $2,330.00</td>
</tr>
<tr>
<td>Aerated Blowers</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Materials</td>
<td>LS</td>
<td>1.00</td>
<td>$1,189,740.00</td>
<td>$1,189,740.00</td>
<td>0.01 $11,897.40</td>
<td>1,000 $1,189,740.00</td>
</tr>
<tr>
<td>Labor to Install</td>
<td>LS</td>
<td>1.00</td>
<td>$25,000.00</td>
<td>$25,000.00</td>
<td>0.01 $250.00</td>
<td>1,000 $25,000.00</td>
</tr>
<tr>
<td>Sludge Dewatering System</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Materials</td>
<td>LS</td>
<td>1.00</td>
<td>$241,890.00</td>
<td>$241,890.00</td>
<td>0.01 $2,418.90</td>
<td>1,000 $241,890.00</td>
</tr>
<tr>
<td>Labor to Install</td>
<td>LS</td>
<td>1.00</td>
<td>$5,608.00</td>
<td>$5,608.00</td>
<td>0.01 $56.08</td>
<td>1,000 $5,608.00</td>
</tr>
<tr>
<td>UV Equipment, Jo Crane</td>
<td>LS</td>
<td>1.00</td>
<td>$114,246.00</td>
<td>$114,246.00</td>
<td>0.01 $1,142.46</td>
<td>1,000 $114,246.00</td>
</tr>
<tr>
<td>Labor to Install</td>
<td>LS</td>
<td>1.00</td>
<td>$8,565.00</td>
<td>$8,565.00</td>
<td>0.01 $85.65</td>
<td>1,000 $8,565.00</td>
</tr>
<tr>
<td>Parshall Flume</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>Materials</td>
<td>LS</td>
<td>1.00</td>
<td>$1,700.00</td>
<td>$1,700.00</td>
<td>0.01 $170.00</td>
<td>1,000 $1,700.00</td>
</tr>
</table>