Text from the PDF text layer; check the PDF for anything that matters.§ 6.2 Guaranteed Maximum Price
The Construction Manager guarantees that the Contract Sum shall not exceed the Guaranteed Maximum Price set
forth in the Guaranteed Maximum Price Amendment, subject to additions and deductions by Change Order as
provided in the Contract Documents. Costs which would cause the Guaranteed Maximum Price to be exceeded shall
be paid by the Construction Manager without reimbursement by the Owner.
All savings from the Guaranteed Maximum Price shall return to the Owner.
§ 6.3 Changes in the Work
§ 6.3.1 The Owner may, without invalidating the Contract, order changes in the Work within the general scope of the
Contract consisting of additions, deletions or other revisions. The Owner shall issue such changes in writing. The
Construction Manager may be entitled to an equitable adjustment in the Contract Time as a result of changes in the
Work.
§ 6.3.1.1 The Architect may order minor changes in the Work as provided in Article 7 of AIA Document A201–
2017, General Conditions of the Contract for Construction.
§ 6.3.2 Adjustments to the Guaranteed Maximum Price on account of changes in the Work subsequent to the
execution of the Guaranteed Maximum Price Amendment may be determined by any of the methods listed in Article
7 of AIA Document A201–2017, General Conditions of the Contract for Construction.
§ 6.3.3 Adjustments to subcontracts awarded on the basis of a stipulated sum shall be determined in accordance with
Article 7 of A201–2017, as they refer to “cost” and “fee,” and not by Articles 6 and 7 of this Agreement.
Adjustments to subcontracts awarded with the Owner’s prior written consent on the basis of cost plus a fee shall be
calculated in accordance with the terms of those subcontracts.
§ 6.3.4 In calculating adjustments to the Guaranteed Maximum Price, the terms “cost” and “costs” as used in Article
7 of AIA Document A201–2017 shall mean the Cost of the Work as defined in Article 7 of this Agreement and the
term “fee” shall mean the Construction Manager’s Fee as defined in Section 6.1.2 of this Agreement.
§ 6.3.5 If no specific provision is made in Section 6.1.3 for adjustment of the Construction Manager’s Fee in the case
of changes in the Work, or if the extent of such changes is such, in the aggregate, that application of the adjustment
provisions of Section 6.1.3 will cause substantial inequity to the Owner or Construction Manager, the Construction
Manager’s Fee shall be equitably adjusted on the same basis that was used to establish the Fee for the original Work,
and the Guaranteed Maximum Price shall be adjusted accordingly.
ARTICLE 7 COST OF THE WORK FOR CONSTRUCTION PHASE
§ 7.1 Costs to Be Reimbursed
§ 7.1.1 The term Cost of the Work shall mean costs necessarily incurred by the Construction Manager in the proper
performance of the Work. The Cost of the Work shall include only the items set forth in Sections 7.1 through 7.7.
All trade contracts will be bid and based on a lump sum value; only allowances, General Requirements, or other
activities performed on a time and material basis will be tracked on a reimbursable basis.
§ 7.1.2 Where, pursuant to the Contract Documents, any cost is subject to the Owner’s prior approval, the
Construction Manager shall obtain such approval in writing prior to incurring the cost.
§ 7.1.3 Costs shall be at rates not higher than the standard rates paid at the place of the Project, except with prior
approval of the Owner.
§ 7.2 Labor Costs
§ 7.2.1 Wages or salaries of construction workers directly employed by the Construction Manager to perform the
construction of the Work at the site or, wages paid for labor involved in expediting material and equipment for the
project from the Construction Manager’s yard and maintenance facilities. Labor, as identified throughout Article
7.1, will be billed as set forth in the attached Exhibit 1 – Labor Rate Schedule, which in addition to wages paid and
attendant burden includes charges for overhead and/or profit in addition to the fee for any work that is not performed
on a lump sum basis.
AIA Document A133 – 2019. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American
Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This
draft was produced at 10:57:51 ET on 09/18/2024 under Order No.4104244063 which expires on 01/20/2025, is not for resale, is licensed for 12
one-time use only, and may only be used in accordance with the AIA Contract Documents ® Terms of Service. To report copyright violations, e-
mail [email protected].
User Notes: (3B9ADA45)
Sources
- sharepoint (J-1 - Miron Contract - Recreation Center - A133.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.