Text from the PDF text layer; check the PDF for anything that matters.Work remaining to be completed or corrected, and to determine what temporary facilities, tools, equipment and
construction machinery are to remain at the Site pending completion of the Work;
.2 take actions necessary, or that the Owner may direct, for the protection and preservation of the Work,
and any stored materials and equipment;
.3 remove any tools, equipment and construction machinery from the Site as directed by the Owner; and
.4 except as otherwise directed by the Owner, terminate all existing subcontractors and purchase orders and
enter into no further subcontracts or purchase orders.
§ 14.2.4 When the Owner terminates the Contract for one of the reasons stated in Section 14.2.1, the Contractor shall
not be entitled to receive further payment until the Work is finished and the costs of completion have been
established.
§ 14.2.5 If the unpaid balance of the Contract Sum exceeds costs of finishing the Work, including compensation for
the Architect’s services and expenses made necessary thereby, and other damages incurred by the Owner and not
expressly waived, such excess shall be paid to the Contractor. If such costs and damages exceed the unpaid balance,
the Contractor shall pay the difference to the Owner. The amount to be paid to the Contractor or Owner, as the case
may be, shall be certified by the Initial Decision Maker, upon application, and this obligation for payment shall
survive termination of the Contract.
§ 14.3 Suspension by the Owner for Convenience
§ 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in
whole or in part for such period of time as the Owner may determine.
§ 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by
suspension, delay, or interruption under Section 14.3.1. Adjustment of the Contract Sum shall include profit. No
adjustment shall be made to the extent
.1 that performance is, was, or would have been, so suspended, delayed, or interrupted, by another cause
for which the Contractor is responsible; or
.2 that an equitable adjustment is made or denied under another provision of the Contract.
§ 14.4 Termination by the Owner for Convenience
§ 14.4.1 The Owner may, at any time, terminate the Contract for the Owner’s convenience and without cause.
§ 14.4.2 Upon receipt of notice from the Owner of such termination for the Owner’s convenience, the Contractor
shall
.1 cease operations as directed by the Owner in the notice and, if required by the Owner, participate in an
inspection of the Work with the Owner and Architect to record the extent of completion thereof, to identify
the Work remaining to be completed or corrected, and to determine what temporary facilities, tools,
equipment and construction machinery are to remain at the Site pending completion of the Work;
.2 take actions necessary, or that the Owner may direct, for the protection and preservation of the Work,
and any stored materials and equipment;
.3 remove any tools, equipment and construction machinery from the Site as directed by the Owner; and
.4 except as otherwise directed by the Owner, terminate all existing subcontractors and purchase orders and
enter into no further subcontracts or purchase orders.
§ 14.4.3 In case of such termination for the Owner’s convenience, the Owner shall pay the Contractor for Work
properly executed plus all out-of-pocket expenses directly related to the termination, but Owner shall have no
obligation to pay or reimburse Contractor for lost profits or unabsorbed overhead, or any other consequential or
incidental damages.
ARTICLE 15 CLAIMS AND DISPUTES
§ 15.1 Claims
§ 15.1.1 Definition
A Claim is a demand or assertion by one of the parties seeking, as a matter of right, payment of money, a change in
the Contract Time, or other relief with respect to the terms of the Contract. The term “Claim” also includes other
disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. The
AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017.
All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract
Documents” are trademarks of The American Institute of Architects. This draft was produced at 15:45:01 ET on 01/14/2025 under Order 37
No.4104244063 which expires on 02/28/2025, is not for resale, is licensed for one-time use only, and may only be used in accordance with
the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail [email protected].
User Notes: (3B9ADA0D)
Sources
- sharepoint (J-1 - Miron Contract - Recreation Center - A201.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.