contract agreement · K-6
K-6 - Profession Services Agreement - MSA - North Park Road Construction Observation
Page 3 of 10
Text read by the vision model; check the PDF for anything that matters.2. Complete one (1) Weekly Report of Working Days or Time Limits Report for each week of the project from project start until substantial completion.
3. Utilize Doc Express to upload and process project paperwork each day and throughout the project along with hard copies of project paperwork provided by Contractor.
4. Review and verify material certifications provided by contractor and as required by the Iowa DOT.
5. Review plant reports from certified concrete plant, coordinate QA testing and monitoring, and manage coordination of approval from the Iowa DOT.
6. Review and schedule beam tests during concrete pour and paving operations based on the attached proposal from Terracon Consultants, Inc.
7. Verify Contractors message board for the project and notify the Contractor of any deficiencies throughout project.
8. Preparing Record Drawings showing appropriate record information based on Project annotated record documents received from Contractor and furnishing such Record Drawings to Owner.
9. Complete Project Audit and Closeout with Iowa DOT, consisting of meetings, material preparation, and gathering required information.
III. On-site Construction Observation
A. Upon successful completion of the Bidding and Negotiating Phase, and upon written authorization from Owner, Engineer shall:
1. Visits to Site and Observation of Construction: In connection with observations of Contractor’s Work while it is in progress:
a. Make visits to the Site at intervals appropriate to the various stages of construction as Engineer deems necessary, to observe the progress of Contractor’s executed Work. Such visits and observations by Engineer or the Inspector are not intended to be exhaustive of Contractor’s Work in progress beyond the responsibilities specifically assigned to Engineer in this Agreement and the Contract Documents. Visits are to be limited to spot checking, selective sampling, and similar methods of general observation of the Work based on Engineer’s exercise of professional judgment, as assisted by the Inspector. Based on information obtained during such visits and observations, Engineer will determine in general if the Work is proceeding in accordance with the Contract Documents, and Engineer shall keep Owner informed of the progress of the Work.
b. Engineer shall not, during visits or as a result of observations of Contractor’s Work in progress, supervise, direct, or have control over Contractor’s Work, nor shall Engineer have authority over or responsibility for the means, methods, techniques, sequences, or procedures of construction selected or used by Contractor, for