M-11 - Original Town Schedule - Rathje Construction
Page 1 of 1
Text from the PDF text layer; check the PDF for anything that matters.ID Task Task Name Duration Start May 25, '25 Jun 1, '25 Jun 8, '25 Jun 15, '25 Jun 22, '25 Jun 29, '25 Jul 6, '25 Jul 13, '25 Jul 20, '25 Jul 27, '25 Aug 3, '25 Aug 10, '25 Aug 17, '25 Aug 24, '25 Aug 31, '25
Mode F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMT
1
2 Stage 3 34 days Tue 5/27/25
3 Storm 5 days Tue 5/27/25
4 Water 8 days Tue 6/3/25
5 GradePrep 5 days Fri 6/13/25
6 PCC 8 days Fri 6/20/25
7 Restoration 6 days Wed 7/2/25
8 HMA 3 days Thu 7/10/25
9 Brick Pavers 5 days Tue 7/15/25
10 Stage 4 18 days Tue 7/22/25
11 Water 10 days Fri 6/20/25
12 Storm 6 days Fri 7/4/25
13 Grade Prep 5 days Mon 7/14/25
14 PCC 8 days Mon 7/21/25
15 Restoration 6 days Thu 7/31/25
16 Brick Pavers 5 days Fri 8/8/25
17 HMA 4 days Fri 8/8/25
18 Stage 5 19 days Mon 7/21/25
19 Storm 3 days Mon 7/21/25
20 Grade Prep 3 days Thu 7/24/25
21 PCC 8 days Tue 7/29/25
22 Restoration 6 days Fri 8/8/25
23 HMA 3 days Mon 8/18/25
24 Signs/Striping 3 days Thu 8/21/25
25 Stage 7 5 days Tue 7/29/25
Task Project Summary Manual Task Start-only Deadline
Project: 2025 Schedule Split Inactive Task Duration-only Finish-only Progress
Date: Mon 3/17/25 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 1
Sources
- sharepoint (M-11 - Original Town Schedule - Rathje Construction.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.