contract agreement · K-2
K-2 - Pay Estimate 1 - Nolan's Lawn Care - Permable Pavers Project
Page 3 of 3
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th>ITEM NO.</th>
<th>CONTRACT ITEMS</th>
<th>UNIT</th>
<th>EST QTY</th>
<th>UNIT PRICE</th>
<th>CONTRACTOR's BID PRICE</th>
<th colspan="2">Pay Period #1</th>
<th colspan="2">TOTAL TO DATE</th>
</tr>
<tr>
<th></th>
<th></th>
<th></th>
<th></th>
<th></th>
<th></th>
<th>QTY</th>
<th>AMOUNT</th>
<th>QTY</th>
<th>AMOUNT</th>
</tr>
<tr>
<td colspan="10"><b>Division 1: Halicirad Street</b></td>
</tr>
<tr>
<td>101</td>
<td>Furnish and Install Joint Material, Setting layer, and Permeable Pavers</td>
<td>SY</td>
<td>1,677.78</td>
<td>$50.85</td>
<td>$85,315.11</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>102</td>
<td>Excavation, Class 10</td>
<td>CY</td>
<td>1,200.00</td>
<td>$10.00</td>
<td>$12,000.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>103</td>
<td>4" Sloped Curb and Gutter Section (30" Wide)</td>
<td>LF</td>
<td>523.00</td>
<td>$32.00</td>
<td>$16,736.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>104</td>
<td>Filter Layer IA DOT Grad. #3, Class 2</td>
<td>CY</td>
<td>211.47</td>
<td>$34.00</td>
<td>$7,199.98</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>105</td>
<td>Subbase Layer IA DOT Grad. #13</td>
<td>TON</td>
<td>634.42</td>
<td>$20.00</td>
<td>$12,688.40</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>106</td>
<td>8" Perforated Subdrain</td>
<td>LF</td>
<td>289.00</td>
<td>$16.00</td>
<td>$4,624.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>107</td>
<td>8" Subdrain Clean out, Type A-2</td>
<td>BACH</td>
<td>3.00</td>
<td>$75.00</td>
<td>$225.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>108</td>
<td>6" PCC Pavement</td>
<td>SY</td>
<td>120.00</td>
<td>$48.00</td>
<td>$5,760.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>109</td>
<td>Modified Subbase</td>
<td>SY</td>
<td>106.25</td>
<td>$34.00</td>
<td>$3,601.50</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>110</td>
<td>Impermeable Membrane with Geo-textile</td>
<td>SF</td>
<td>2,015.50</td>
<td>$4.00</td>
<td>$8,062.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>111</td>
<td>Bl-Axial Geogrid</td>
<td>SF</td>
<td>1,833.61</td>
<td>$2.00</td>
<td>$3,667.22</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>112</td>
<td>Curb Ramp Detectable Warnings</td>
<td>SF</td>
<td>20.00</td>
<td>$30.00</td>
<td>$600.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>113</td>
<td>Solvent Based</td>
<td>STA</td>
<td>13.10</td>
<td>$105.00</td>
<td>$1,373.50</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>114</td>
<td>Solvent Based</td>
<td>BACH</td>
<td>2.00</td>
<td>$100.00</td>
<td>$200.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>115</td>
<td>Seeding, Fertilizing, Mulching, Urban</td>
<td>ACRE</td>
<td>0.25</td>
<td>$5,000.00</td>
<td>$1,250.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>116</td>
<td>Mobilization</td>
<td>LS</td>
<td>1.00</td>
<td>$12,000.00</td>
<td>$12,000.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>117</td>
<td>Traffic Control</td>
<td>LS</td>
<td>1.00</td>
<td>$750.00</td>
<td>$750.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>118</td>
<td>Erosion Controls</td>
<td>LS</td>
<td>1.00</td>
<td>$2,750.00</td>
<td>$2,750.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>119</td>
<td>Type A Signs</td>
<td>BACH</td>
<td>2.00</td>
<td>$175.00</td>
<td>$350.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td colspan="10"><b>Division 2: Dog Park</b></td>
</tr>
<tr>
<td>201</td>
<td>Furnish and Install Joint Material, Setting layer, and Permeable Pavers</td>
<td>SY</td>
<td>589.56</td>
<td>$50.85</td>
<td>$29,979.13</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>202</td>
<td>Excavation, Class 10</td>
<td>CY</td>
<td>800.00</td>
<td>$10.00</td>
<td>$8,000.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>203</td>
<td>4" Sloped Curb and Gutter Section (30" Wide)</td>
<td>LF</td>
<td>433.00</td>
<td>$32.00</td>
<td>$13,856.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>204</td>
<td>Filter Layer IA DOT Grad. #3, Class 2</td>
<td>CY</td>
<td>88.00</td>
<td>$34.00</td>
<td>$3,027.20</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>205</td>
<td>Subbase Layer IA DOT Grad. #13</td>
<td>TON</td>
<td>276.37</td>
<td>$20.00</td>
<td>$5,527.40</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>206</td>
<td>8" Perforated Subdrain</td>
<td>LF</td>
<td>1,630.00</td>
<td>$10.00</td>
<td>$16,300.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>207</td>
<td>8" Subdrain Clean out, Type A-2</td>
<td>BACH</td>
<td>1.00</td>
<td>$75.00</td>
<td>$75.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>208</td>
<td>Inlet, SW-512, 24" Dia.</td>
<td>BACH</td>
<td>1.00</td>
<td>$735.00</td>
<td>$735.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>209</td>
<td>6" PCC Pavement</td>
<td>SY</td>
<td>233.00</td>
<td>$32.00</td>
<td>$7,456.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>210</td>
<td>Modified Subbase</td>
<td>SY</td>
<td>407.00</td>
<td>$33.00</td>
<td>$13,431.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>211</td>
<td>Impermeable Membrane with Geo-textile</td>
<td>SF</td>
<td>743.33</td>
<td>$4.00</td>
<td>$2,973.32</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>212</td>
<td>Bl-Axial Geogrid</td>
<td>SF</td>
<td>727.00</td>
<td>$2.00</td>
<td>$1,454.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>213</td>
<td>Curb Ramp Detectable Warnings</td>
<td>SF</td>
<td>92.00</td>
<td>$30.00</td>
<td>$2,760.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>214</td>
<td>Solvent Based</td>
<td>STA</td>
<td>4.62</td>
<td>$105.00</td>
<td>$483.10</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>215</td>
<td>Solvent Based</td>
<td>BACH</td>
<td>2.00</td>
<td>$100.00</td>
<td>$200.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>216</td>
<td>Seeding, Fertilizing, Mulching, Urban</td>
<td>ACRE</td>
<td>0.50</td>
<td>$5,000.00</td>
<td>$2,500.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>207</td>
<td>Mobilization</td>
<td>LS</td>
<td>1.00</td>
<td>$2,995.00</td>
<td>$2,995.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>218</td>
<td>Traffic Control</td>
<td>LS</td>
<td>1.00</td>
<td>$800.00</td>
<td>$800.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>219</td>
<td>Erosion Controls</td>
<td>LS</td>
<td>1.00</td>
<td>$2,750.00</td>
<td>$2,750.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>220</td>
<td>Type A Signs</td>
<td>BACH</td>
<td>2.00</td>
<td>$250.00</td>
<td>$500.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td colspan="10"><b>TOTAL OF THE BASE BID (Total of Items 101-220):</b></td>
<td>$254,724.08</td>
<td>$20,000.00</td>
<td>$274,724.08</td>
</tr>
<tr>
<td>CO1</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>CO2</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>CO3</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>CO4</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>CO5</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>CO6</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td>CO7</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
</tr>
<tr>
<td colspan="10"><b>CHANGE ORDER SUB-TOTAL</b></td>
<td>$0.00</td>
<td>$ -</td>
<td>$0.00</td>
</tr>
<tr>
<td colspan="10"><b>AMOUNT EARNED TOTAL</b></td>
<td>$0.00</td>
<td>$ -</td>
<td>$0.00</td>
</tr>
<tr>
<td>9998</td>
<td>Materials Stored on-site</td>
<td></td>
<td></td>
<td></td>
<td>$16,556.54</td>
<td>$ -</td>
<td>$16,556.54</td>
<td></td>
<td></td>
</tr>
<tr>
<td>9999</td>
<td>Materials Installed on-site (Deduct)</td>
<td></td>
<td></td>
<td></td>
<td>$ -</td>
<td>$ -</td>
<td>$ -</td>
<td></td>
<td></td>
</tr>
<tr>
<td colspan="10"><b>MATERIALS SUB-TOTAL</b></td>
<td>$16,556.54</td>
<td>$ -</td>
<td>$16,556.54</td>
</tr>
<tr>
<td colspan="10"><b>TOTAL</b></td>
<td>$16,556.54</td>
<td>$ -</td>
<td>$16,556.54</td>
</tr>
</table>
Sources
- sharepoint (K-2 - Pay Estimate 1 - Nolan's Lawn Care - Permable Pavers Project.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.