WS - E - Emergency Access Road - Village Drive
Page 1 of 1
Text from the PDF text layer; check the PDF for anything that matters.The plan would be to use the existing grade until we get to the area west of the existing mulch
pile. We’ll grade and shape this area to make a smoother transition up to the existing water tower
road. We’ll also shape a small ditch on the north side of the temporary road and install a temporary
pipe to get storm water from the north side to the south. As discussed, we’ll make the road 20 feet
wide and place 8-inches of Class A Roadstone. We discussed perhaps placing 6 inches and seeing how it
would hold up but I think we’d be better off going with 8 inches right away. Placing 6 inches on the
sandy soils will struggle to carry a fire truck. Below is the cost estimate for the temporary road.
Emergency Rd Qty Unit Unit Price Total
Grading & Shaping 1.00 LS $ 7,500.00 $ 7,500.00
Temp Culvert 1.00 LS $ 750.00 $ 750.00
Cl. A Roadstone (8in depth) 1,650.00 TN $ 16.20 $ 26,730.00
Temp Seeding/Fert/Mulch 1.25 AC $ 1,500.00 $ 1,875.00
Total Est. Cost: $ 36,855.00