engineering report · M-8
M-8 - City Engineer Report
Page 1 of 3
Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISON:
Andrew Inhelder, PE
Office: 319.364.4773
Cell(s): 515.802.0906
[email protected]
DATE:
June 26, 2024
ON-GOING PROJECTS
North Park Road Improvements – James Watters
City did not receive TAP funding for this project and the public information meeting is now scheduled for
June 25th.
Current tasks MSA is working with the City on acquiring necessary Right of Way for the project and
coordination for a Public Involvement Meeting. The meeting has been scheduled for June 26, 2024, from
5-7 pm at City Hall. The meeting will be an open house style meeting where the public can attend and ask
questions regarding the project. Comment cards will be available for the public to leave feedback on the
project.
Army Corp of Engineers Permit has been submitted for the project on 6/18/24
Highway 6 Concept and Cost Estimate – James Watters
Field exam is scheduled for June 26th. James Watters will be at Tiffin City Hall for meeting. Meeting will be
held virtually with other DOT personnel.
DOT confirmed two box culverts will be replaced and the western most culvert will be extended.
MSA submitted D2 Field Exam plans to Mark Harle with DOT on 6/18/24.
Comprehensive Water System Evaluation – Clint Wienen
The Preliminary Engineering Report (PER) has been submitted to the DNR for their review and approval.
The DNR requested that a waiver request be submitted for consideration for installing the base slab of the
clearwell below the 100-year flood elevation. The waiver request has been submitted but we have not
received any comments regarding the waiver request or the PER.
Reverse Osmosis Water Treatment Plant Design – Clint Wienen
A 60% design review meeting was held on June 4th. Comments provided will be incorporated into the final
design. We are currently planning to submit the plans and specifications to the DNR in mid-July for
permitting. The intent is to bid out the control package and the generator in June/July so the equipment
can be delivered in a timely manner in order for the treatment plant to go online in 2025.
Pedestrian light (RRFB) on eastern leg of roundabout at Hwy 6 & Park Road. – Andrew Inhelder
City Council approved RRFBs. Shop drawings have been sent to the DOT for review/approval. Awaiting
DOT Review/approval. Contractor to submit an updated schedule to install RRFBs.
PROJECT UPDATE
Page 1 of 3