Text from the PDF text layer; check the PDF for anything that matters.OPINION OF PROBABLE PROJECT COSTS
Site Work - Fill*: 31,000 CY x $20 - $25/SQ. FT. $620,000 - $775,000
Phase 1: 45,706 SQ. FT. x $190/SQ. FT. $8,684,140
Total Cost*: $9,304,140 - $9,459,140
*Fill calculated for all 3 phases – subject to change