I-2 - Resolution 2021-056 - Electric Facilities Construction and Payment Agreement
Page 8 of 8
Text read by the vision model; check the PDF for anything that matters.Date 18-Mar-21
Quote Estimate or Final 0
Customer CIPCO
RFI/Issue/QA-QC Report 0
Customer number 0
Structure Number 186 & 188
Release 0
Service Job 0
Project Linn Co Loop Project
Work Description modify 2 structutes
186 add 2 wraps
smooth 1 set of thru vangs
188 move clip and loops
add 6 PIBs
Work schedule start 0-Jan-00
complete 0-Jan-00
<table>
<tr>
<th>item</th>
<th>description</th>
<th>units</th>
<th>charge</th>
<th>charge ext'd</th>
</tr>
<tr>
<td rowspan="3">personnel</td>
<td>welder</td>
<td>71</td>
<td>$ 185.00</td>
<td>$ 13,135.00</td>
</tr>
<tr>
<td>inspector</td>
<td>0</td>
<td>$ 195.00</td>
<td>$ -</td>
</tr>
<tr>
<td>travel time</td>
<td>welder</td>
<td>14</td>
<td>$ 185.00</td>
<td>$ 2,590.00</td>
</tr>
<tr>
<td></td>
<td>inspector</td>
<td>0</td>
<td>$ 195.00</td>
<td>$ -</td>
</tr>
<tr>
<td>travel charge</td>
<td>welder</td>
<td>8</td>
<td>$</td>
<td>$ -</td>
</tr>
<tr>
<td></td>
<td>inspector</td>
<td>0</td>
<td>$</td>
<td>$ -</td>
</tr>
<tr>
<td colspan="2">Service Truck</td>
<td>6</td>
<td>$ 390.00</td>
<td>$ 2,340.00</td>
</tr>
<tr>
<td colspan="2">Rental Auto</td>
<td>0</td>
<td>$ 150.00</td>
<td>$ -</td>
</tr>
<tr>
<td colspan="2">Subsistence no overnight</td>
<td>welder</td>
<td>1</td>
<td>$ 125.00</td>
<td>$ 125.00</td>
</tr>
<tr>
<td></td>
<td>inspector</td>
<td>0</td>
<td>$ 125.00</td>
<td>$ -</td>
</tr>
<tr>
<td colspan="2">Subsistence w/Overnight</td>
<td>welder</td>
<td>6</td>
<td>$ 280.00</td>
<td>$ 1,680.00</td>
</tr>
<tr>
<td></td>
<td>inspector</td>
<td>0</td>
<td>$ 280.00</td>
<td>$ -</td>
</tr>
<tr>
<td colspan="4">Material, Consumables, Finish, additional equipment & charges</td>
<td>$ 242</td>
</tr>
</table>
TOTAL $ 20,112
Quote provided is based on reasonable expectations and the assumption that site is accessible for performance of work. Any additional activities and/or costs required for performance of quoted work; including equipment, personnel, excavation / construction to access work area, down time, per diem, etc.; will be provided by and the responsibility of customer. Any additional costs incurred by Meyer will be the responsibility of customer.”