contract agreement · K-3
K-3 - Change Order #1 - Nolan's Lawn Care - Permeable Pavers Project
Page 1 of 1
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 9/29/2021
Change Order No: 1 (ONE)
Agreement Date: 12/15/2020
PROJECT: Permeable Paver Parking Project HFC#15218.205
OWNER: City of Tiffin, IA
CONTRACTOR: Nolan's Lawn Care
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Contractor was asked to delay work on the Dog Park parking lot until the Trail Phase 6 project was substantially complete. The Railroad Street lot is substantially complete.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $__________________________
CONTRACT with LAST CHANGE ORDER: $__________________________
THIS CHANGE ORDER AMOUNT: $__________________________
NEW CONTRACT PRICE: $__________________________
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): 31 days
NEW Completion Date: October 31, 2021
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER: ________________________________
CONTRACTOR: __________________________
ENGINEER: ______________________________