PROJECT UPDATE
NORTH PARK ROAD IMPROVEMENTS – JAMES WATTERS
Delays in the installation of the pedestrian tunnel have led to a change in staging. Stage 2 (the section
between the Tiffin Elementary main entrance and Highway 6) has been approved to begin this summer.
This schedule adjustment should allow for the paving of the proposed roundabout and all mainline and
frontage road pavement south to Highway 6.
Pavement south of the Tiffin Elementary School main entrance has been removed. Both school sites are
now only accessible from the north via the Oak Hill main entrance. Traffic control appropriate for the
closure at Highway 6 has been or will soon be applied. Access to both schools by the Fire Marshall is to be
maintained throughout construction. Requirements for access have been conveyed to construction
personnel.
It is anticipated that when school resumes in August, access by car and bus to Tiffin Elementary will be open
from the south and access by car to Oak Hill Elementary will be open from the north. When Stage 1A, 1B,
and 2 (everything south of Oak Hill’s main entrance) is completed, Stage 3 may begin and access to all school
entrances will be available from the south only.
Damage to fiber lines, a handhole box, and two trees was reported by CCACSD staff. Efforts to address this
damage are in progress.
PROJECT UPDATE
Page 2 of 4
Sources
- revize: M.9 - Engineer's Report (QmQ1mswieXvMnrN8NGK7dbDgVFA8bw.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (M-9 - City Engineer Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: M Reports from City Personnel
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.