Draft chapter 115: Electric Franchise (transmission System)
§ 115.09 Entire Agreement
The 2026 draft's § 115.09 beside the current code's § 115.09: removed words are struck through, added words underlined.
Comparison with a draft: not adopted. The archive holds no public hearing, ordinance or vote adopting the recodified Code through the October 20, 2026 meeting packet. Until one is adopted, every page here compares the consolidated code with a draft that can still change: the revised draft with the October 6 changes is not in the archive.
A comparison with the August 2026 draft recodification prepared by Iowa Codification for the City. The draft has not been adopted and can still change; the current code (unofficial compilation) governs until a recodified Code is adopted. Matches between sections are made by machine from the texts and are reviewed where uncertain.
Wording changed minor wording (96% same words)
What changed
(Ch. 115 - Ord. 2012-309 – Jan. 14 Supp.)
Word-level comparison of the current text with the draft's; spacing and paragraph breaks come from the documents' text. Footnotes are left out.
Current code
§ 115.09 Entire Agreement
This chapter sets forth and constitutes the entire agreement between the Company and the City of Tiffin with respect to the rights contained herein, and may not be superseded, modified or otherwise amended without the approval and acceptance of the Company. Upon acceptance by the Company, this chapter shall supersede, abrogate and repeal any prior electric system ordinance between the Company and the City as of the date this chapter is accepted by the Company. Notwithstanding the foregoing, in no event shall the City enact any ordinance or place any limitations, either operationally or through the assessment of fees, that create additional burdens upon the Company or that delay utility operations.
(Ch. 115 - Ord. 2012-309 – Jan. 14 Supp.)
2026 draft
§ 115.09 Entire Agreement
This chapter sets forth and constitutes the entire agreement between the Company and the City with respect to the rights contained herein, and may not be superseded, modified, or otherwise amended without the approval and acceptance of the Company. Upon acceptance by the Company, this chapter shall supersede, abrogate, and repeal any prior electric system ordinance between the Company and the City as of the date this chapter is accepted by the Company. Notwithstanding the foregoing, in no event shall the City enact any ordinance or place any limitations, either operationally or through the assessment of fees, that create additional burdens upon the Company or that delay utility operations.
Back to draft chapter 115 · All changes
Data last updated October 23, 2026. Built from the archive's documents; see how the data is built.