Consideration of Grinder for Lift Station as currently Budgeted for in FY 25-26 – Motion to Approve — Quote
Page 1 of 2
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-7
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: July 31, 2025
AGENDA ITEM: Consideration of Grinder for Lift Station as currently Budgeted for in FY 25-26
ACTION: Motion
Overview
As part of the FY 25–26 approved budget, the City of Tiffin allocated funds for the purchase and
installation of a grinder unit for one of the city’s lift stations. This equipment is intended to
improve operational efficiency and reduce maintenance issues caused by debris and solids in the
wastewater system.
Quote Summary
The City received a formal quote from Iowa Pump Works, LLC dated March 12, 2025, for the
following equipment and services:
• Vogelsang XRipper XRC100-320QD Grinder: $35,167.06
• Mounting System: $12,391.37
• Control Panel: $3,110.97
• Installation Services (3 technicians × 10 hours): $9,120.50
Total Quote Amount: $63,819.61
(Shipping and applicable taxes not included; lead time is 6–7 weeks)
Recommendation
Staff recommends approval of the quote from Iowa Pump Works, LLC for the purchase and
installation of the Vogelsang XRipper grinder system for the lift station. This equipment will
help reduce blockages, improve pump longevity, and enhance overall system reliability.
ATTACHMENTS: Quote
1
Sources
- revize: Quote (Z1oJ6qFOUAge75QEXj4muJsWcQ0BIB.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-7 - Staff Report - Grinder for Lift Station - Quote.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Consideration of Grinder for Lift Station as currently Budgeted for in FY 25-26 –...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.