Overview
This report presents Pay Application #5 submitted by Boomerang Construction for work
completed on the North Park Road project between June 22, 2025, and July 26, 2025. The
application is currently under review and pending approval.
Work Summary
This pay application includes progress on several key items, including:
• Continued excavation and grading work
• Installation of water service stubs (1” and 2”)
• Installation of 8” and 12” gate valves
• Fire hydrant assembly installations
No retainage or liquidated damages are being applied at this time. There are no adjustments or
recoveries noted for this period.
Recommendation
Staff recommends approval of Pay Application #5 in the amount of $786,370.20 to Boomerang
Construction for work completed on the North Park Road project. This payment is consistent
with the progress made and verified by project oversight.
ATTACHMENTS: Pay Application
1
Sources
- revize: Pay Application (e1DpWZHhpKPUcBjFqogADBPWcyCU1s.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-4 - Staff Report - Pay Application # 5 - Boomerang Corp - North Park Road Improvements Project.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Consideration of Pay Application #5 – Boomerang Corp, North Park Road Improvement...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.