Discussion and Consideration of Change Order #2 – Cornerstone Excavating – Tiffin Forevergreen Road Grading Project and Council Action as Needed — K.3
Page 1 of 2
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-3
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: May 15, 2026
AGENDA ITEM: Discussion and Consideration of Change Order #2 – Cornerstone Excavating
– Tiffin Forevergreen Road Grading Project and Council Action as Needed
ACTION: Motion
Background
The City of Tiffin is currently completing the Forevergreen Road Grading Project with
Cornerstone Excavating, Inc. serving as the contractor.
Change Order No. 2 has been submitted to address additional erosion control measures required
on the project site. These items were necessary to stabilize disturbed areas and ensure
compliance with stormwater and site management requirements.
The additional work included in this change order reflects necessary field adjustments related to
erosion control and site conditions. These types of improvements are common in large grading
projects, particularly when managing stormwater and long-term stabilization.
The costs are consistent with the scope of work and reflect standard unit pricing for erosion
control measures and site restoration activities.
No additional working days were requested as part of this change order.
Recommendation
Staff recommends approval of Change Order No. 2 in the amount of $29,712.25 for the
Forevergreen Road Grading Project.
ATTACHMENTS: Change Order
1
Sources
- revize: K.3 (RcIM4pK2Uv4d6Y2NQz8ma3ATbywexa.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-3 Discussion and Consideration of Change Order #2 – Cornerstone Excavating – Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.