Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISON:
Andrew Inhelder, PE
Office: 319.364.4773
Cell: 515.802.0906
[email protected]
DATE:
July 31, 2026
ON-GOING PROJECTS
REVERSE OSMOSIS WATER TREATMENT PLANT DESIGN – CLINT WIENEN
The precast for the pumphouse and east addition on the existing building has been placed and grouted.
Trusses and sheathing are beginning to be set in both of these places. The fluoride room on the exiting
building has been framed. MCC panels have been set in the new MCC room. Masonry walls have begun to
be framed up. The old plant generator has been moved to Well 5. Other work to be completed in the next
coming weeks is the completion of masonry walls, driveway paving, and delivery of RO skids.
Substantial Completion date for the project is September 30, 2026.
SYSTEMWIDE SANITARY SEWER MODEL – ERIC THOMPSON
MSA has updated the modeling to include the Potter Creek interceptor. MSA is supporting ongoing
development and coordination for new lift stations to the west of the City limits.
VILLAGE DRIVE & ROBERTS FERRY ROAD SIGNAL DESIGN – ANDREW INHELDER
Project was awarded to Neumiller Electric, Inc on May 19th, 2026. Contractor and MSA are working
through shop drawing submittal and review. A pre-construction meeting will be scheduled closer to the
anticipated project start date.
Substantial Completion date for the project is October 2, 2026.
HIGHWAY 6 CONCEPT AND COST ESTIMATE – JAMES WATTERS
Final plans for letting are due to the DOT on August 4, 2026. The project will open bids for project in mid
October
DOT is currently working on the construction agreement with the City and will be submitting to the City
for signature when ready. This agreement will put in place construct cost splits between the City and DOT.
PROJECT UPDATE
Page 1 of 5
Sources
- revize: L-2 (DrKdNwm0f5CoW9LyYbJp8jFQLaqtSf.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-2 City Engineer's Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.