contract agreement · K-4
K-4 - Change Order 1, Rathje Construction - Original Town Phase 2
Page 1 of 2
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER #1
DATE: 2/22/2021
Change Order No: 1
Agreement Date: May 5, 2020
PROJECT: Original Town Urbanization Project: Phase Two – 18218.1312
OWNER: City of Tiffin, IA
CONTRACTOR: Rathje Construction Co.
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Replace Milling/Stabilization with 12” Modified Subbase and Geogrid
Modification of Staging: Combine Stages and 2 into a single Stage 1, Stage 3 becomes Stage 2, and combine Stages 4 and 5 into a single Stage #3. Change Completion Date.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $1,824,618.96
CONTRACT with LAST CHANGE ORDER: $1,824,618.96
THIS CHANGE ORDER AMOUNT: $(10,000.00)
NEW CONTRACT PRICE: $1,824,608.96
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): N/A
NEW Completion Date: December 15, 2021
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER: ________________________________
CONTRACTOR: See Attached
ENGINEER: ________________________________