contract agreement · K-7
K-7 - Change Order 7 - Roberts Ferry Road - Vieth Construction
Page 1 of 4
Text from the PDF text layer; check the PDF for anything that matters. Accounting ID No.(5-digit number):
Form 831240 (08-18)
CHANGE ORDER Change Order No.:
For Local Public Agency Projects
No.: 7 Non-Substantial:
Substantial: Administering Office
Concurrence Date
Accounting ID No. (5-digit number):35177 Project Number: STP-U-7662(612)--70-52
Contract Work Type: PCC Pavement- Grade & Replace Local Public Agency: City of Tiffin
Contractor: Vieth Construction Corp. Date Prepared: January 12, 2021
You are hereby authorized to make the following changes to the contract documents.
A - Description of change to be made:
0010-Increase Item for Clearing & Grubbing
0020-Increase Item for Clearing & Grubbing
0070-Decrease Item for Modified Subbase
0120-Decrease Item for Standard or Slip Form PCC Pavement, Class C, Class 3 Durability, 9 Inch
0140-Delete Item for Hot Mix Asphalt, Driveway
0430-Decrease Item Removal of Sidewalk
0440-Decrease Item for Sidewalk, PCC, 4 inch
0450-Decrease Item for Sidewalk, PCC, 6 inch
0470-Increase Item for Driveway, PCC, 6 inch
0480-Decrease Item for Removal of Paved Driveway
8005-Add item for Payment Adjustment Incentive/Disincentive for PCC Pavement Thickness (By Schedule)
8006-Add item for Price Adjustment PCC Pavement Smoothness
8007-Add item for Price Adjustment Non-Complying Traffic Control Diary
8998-Add item for Price Adjustment Liquidated Damages
B - Reason for change:
0010-0020-During the course of construction, it was determined that additional trees within the project limits were in conflict with
the work of the project. The Contractor was instructed to remove the trees in conflict.
0070-Original quantity for this item was determined to be in error.
0120-Less pavement was installed than originally planned.
0140-During the course of the project, the property changed hands and new owner opted for PCC driveway instead of asphalt.
0430-Less sidewalk was removed than planned to construct the proposed sidewalks.
0440-0450-Less sidewalk than planned was installed.
0470-Material of one driveway was changed to PCC at the request of the property owner; other driveways were constructed slightly
larger than planned.
0480-Less driveway was removed than planned to construct the proposed driveways. The original quantity may have been in error.
8005-The Contractor qualifies for a thickness disincentive based upon the PCC pavement sample measurements.
8006-The plans specify that PCC pavement smoothness applies to the project. Based upon the low traffic speeds and relatively short
project length, the city and contractor mutually agree to waive the profilometer pavement profile and instead perform a 10' straight
edge 1/8" bump test per Standard Specification 2301.03,H.,4.
8007-The Contractor's daily traffic control diary is incomplete. There are no reviews documented over weekends and holidays, and
there are gaps in the diary entries from 5/24/19 through 6/3/19 and 7/12/19 through 10/3/19.
8998-The Contractor exceeded the allowed number of working days by 39.0 days.
C - Settlement for cost(s) of change as follows with items addressed in Sections F and/or G:
0010-0020 Contract Unit Price
0070 Contract Unit Price
0120 Contract Unit Price
0140-Contract Unit Price
0430-0450 Contract Unit Prices
0470-0480 Contract Unit Prices
8005-Agreed Unit Price Credit
8006-Agreed Unit Price Credit
Page 1 of 4