WS - D - Opinion of Probabe Costs - PW Facility
Page 1 of 2
Text from the PDF text layer; check the PDF for anything that matters.Page 1 of 2 Project Management Spreadsheet Tiffin Public Services
www.MartinGardnerArch.com (Opinion of Probable Costs) 9/1/2021
Statements of probable construction cost prepared by Martin Gardner Architecture, P.C. represents our best judgments as design professionals familiar with the construction industry. However, neither Martin Gardner
Architecture, P.C. nor the Owner has control over the cost of labor, materials or equipment, over the contractor's method of determining bid prices, or over competitive bidding, market or negotiating conditions. Prices/bids
may be affected due to uncertainty in the supply chain as a result of social distancing, stay at home orders, or other safety accommodations in relation to the Covid-19 pandemic and its effects on manufacturing, delivery, and
the backlog of goods and services. The current disaster response occurring in the area also makes the bidding market more volatile at this time. Accordingly, Martin Gardner Architecture, P.C. cannot and does not warrant or
represent that bids will not vary from the project budget proposed, established or approved by the owner, if any, or from any statement of probable construction cost prepared by Martin Gardner Architecture.
Building Square Footage 16,490
Quantity Unit Unit Price Total
SITE WORK
MOBILIZATION 1 EA $17,850.00 $17,850
GRIND CURB 230 LF $10.50 $2,415
REMOVE GRAVEL, STOCK PILE, AND RESPREAD 1 LS $3,150.00 $3,150
REMOVE PCC 345 SY $15.75 $5,434
ADJUST INTAKE 1 EA $787.50 $788
CHAN LINK FENCE 6 FT HT, BARBED WIRE 520 LF $28.35 $14,742
SLIDING FENCE GATE AND OPERATOR INCLUDING POWER AND CONTROLS 2 EA $12,600.00 $25,200
IMPORT EARTHWORK 2,700 CY $12.60 $34,020
8" PCC 990 SY $63.00 $62,370
MODIFIED SUBBASE 310 TON $31.50 $9,765
PCC CURB 105 LF $28.35 $2,977
PCC SIDEWALK 30 SY $52.50 $1,575
PAVEMENT DUBDRAIN 250 LF $10.50 $2,625
SEEDING BY OWNER CY $0.00 $0
Site work Subtotal $182,910
SUBSTRUCTURE
OVERHEAD DOOR OPERATORS DOOR OPERATORS, OH DOORS IN BUILDING PACKAGE 8 EA $2,030.00 $16,240
SECOND FLOOR CONSTRUCTION JOISTS, SHEATHING 2,030 SF $8.81 $17,884
STAIRS WOOD STAIRS 1 EA $2,395.00 $2,395
SUPERSTRUCTURE
PRE-ENGINEERED WOOD BUILDING BUILDING, EXTERIOR INSULATION, OH DOORS, WINDOW, MAN DOORS 1 EA $660,000.00 $660,000
Superstructure Subtotal $660,000
EXTERIOR ENCLOSURE
BUILDING SLAB CONCRETE 3500 PSI, REBAR, FORMS 14,775 SF $6.35 $93,821
BUILDING FOUNDATION CONCRETE 544 LF $96.80 $52,659
GEOPIERS 60 EA $695.50 $41,730
PERIMETER INSULATION 2" PEREMETER INSULATION, 3' VERTICAL AND 2' HORIZONTAL UNDER SLAB 3,264 SF $2.24 $7,311
Exterior Enclosure Subtotal $195,522
INTERIORS
ACOUSTICAL CEILING TILE 3,580 SF $3.35 $11,993
Interiors Subtotal $11,993
SERVICES
Division 21 - Fire Suppression System FULL SPRINKLER SYSTEM, INCLUDES BACKFLOW PREVENTOR $55,000
ALL ABOVE-GRADE PIPING AND INSULATION, EXCLUDES OWNER PROVIDED FIXTURES, EXCLUDES
Division 22 - Plumbing $23,000
UNDERGROUND PLUMBING PIPING
FULL HVAC FOR OFFICE AREA (FURN ACES, ERV'S, DUCTWORK, DIFFUSERS, RADIENT HEATERS AND VEHICLE
Division 23 - HVAC EXHAUST SYSTEM FOR SHOP AND WASH BAY
$122,000
INCLUDE ELECTRICAL SERVICE ENTRANCE, PANELS, LIGHTS, LIGHTING CONTROLS AND RECEPTABLES,
Division 26 - Electrical $214,000
INCLUDES GENERATOR, INCLUDES FUTURE PV PROVISIONS
Division - 27 Communications/28 Electrical - Safety & Security INCLUDES FULL FIRE ALARM, SERCURITY CAMERAS, DATA OUTLETS AND ASSOCIATED RACK AND SWITCHES. $61,500
Services Subtotal $475,500
ALTERNATES / BY OWNER / EQUIPMENT
PROTECTION BOLLARDS 4 PER OVERHEAD DOOR 32 EA $842.90 $26,973
CRANE OVERHEAD CRANE, 5 TON CAPACITY, 15' TRAVEL 1 EA $8,400.00 $8,400
SEFAC LIFT SYSTEM 4 EA $4,536.00 $18,144
WALLS BY OWNER, STUDS, G.B., INSULATION 516 LF $145.00 $74,820
PAINTING BY OWNER 11,750 SF $2.02 $23,735
APPLIANCES BY OWNER STOVE, MICROWAVE, REFRIGERATOR, BY OWNER 1 TOT $1,900.00 $2,200
HARDWARE BY OWNER AVERAGE STANDARD HARDWARE COSTS PER DOOR 31 EA $898.00 $27,838
INTERIOR DOORS BY OWNER 33 EA $420.00 $13,860
EXTERIOR HARDWARE BY OWNER AVERAGE STANDARD EXTERIOR HARDWARE COSTS PER DOOR 3 EA $1,400.00 $4,200
VCT BY OWNER OFFICE BATHROOMS, BREAKROOM 675 SF $11.74 $7,925
VCT BY OWNER OFFICE HALLWAYS 590 SF $13.90 $8,201
CARPET BY OWNER OFFICE 185 SY $43.05 $7,964
TOILET ACCESSORIES BY OWNER GRAB BARS, TP DISPENSER, SOAP DISPENSOR, PAPERTOWEL DISPENSER 1 ALL $2,390.00 $2,390
LOCKERS BY OWNER 15 EA $597.50 $8,963
SIGNAGE BY OWNER RR's, LOCKER ROOM, SHOWER ROOM, MECHANICAL, SPRINKLER 10 EA $83.50 $835
BREAKROOM CASEWORK BY OWNER 9 LF $518.50 $4,667
BY OWNER - INCLUDES ALL UNDERGROUND PLUMBING MATERIAL INCLUDING TRENCH DRAINS AND
DIVISION 22 - PLUMBING 1 EA $52,000.00 $52,000
SAND/OIL INERCEPTOR
DIVISION 26 - ELECTRICAL BY OWNER - INCLUDES BRANCH CIRCUIT WIRING MATERIALS 1 EA $11,500.00 $11,500
ALTERNATES Subtotal $304,614
GENERAL REQUIREMENTS
SUPERINTENDENT 12 WK $3,225.00 $38,700
ON-SITE OFFICE POD & EQUIPMENT 6 MO $800.00 $4,800
PLAN PRINTING / COPYING 1 EA $1,200.00 $1,200
WATER STATION 6 MO $500.00 $3,000
TEMPORARY TOILET AND WASHING STATION 6 MO $550.00 $3,300
GENERAL TRUCKING 6 MO $1,500.00 $9,000
TEMPORARY HEAT AND ENCLOSURE 5 MO $2,000.00 $10,000
SNOW REMOVAL OR PUMP WATER 1 EA $5,000.00 $5,000
CLEAN UP & RUBBISH REMOVAL 6 EA $1,200.00 $7,200
FINAL CLEANING 1 EA $1,200.00 $1,200
MISCELLANEOUS EQUIPEMENT 1 EA $3,000.00 $3,000
FIRE EXTINGUISHERS DURING CONSTRUCTION 4 EA $500.00 $2,000
FIRST AID EQUIPEMENT 1 EA $500.00 $500
CONTRACTORS RR LIABILITY INSURANCE INSURANCE TO CONSTRUCT NEAR RAILROAD TRACKS 1 EA $10,500.00 $10,500
General Requirements Subtotal $99,400
Project Subtotal $1,966,458
700 11th St., Ste. 200 11502 390th St.
Marion, IA 52302 Strawberry Point, IA 52076
P: (319) 377-7604 P: (563) 933-4712
F: (319) 377-1175 F: (563) 933-2052
Sources
- sharepoint (WS - D - Opinion of Probabe Costs - PW Facility.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.