contract agreement · K-2
K-2 - Change Order 6, Rathje Construction - Original Town Urbanization
Page 1 of 2
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 14 September, 2021
Change Order No: 6 (Six)
Agreement Date: 5 May, 2020
PROJECT: Original Town Urbanization Project: Phase Two HFC#12218.13123
OWNER: City of Tiffin, IA
CONTRACTOR: Rathje Construction
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
The existing 4-inch raw watermain is shallow as it crosses Main Street and needs to be relocated to maintain 5-feet of cover for frost protection. The watermain does not have tracer wire and therefore could not be properly located during project design. Approximately 200 LF of watermain will be relocated. Unit price includes labor, equipment and materials.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $1,824,618.96
CONTRACT with LAST CHANGE ORDER: $1,845,370.54
THIS CHANGE ORDER AMOUNT: $13,400
NEW CONTRACT PRICE: $1,858,770.54
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): 2 day
NEW Completion Date: 6 June, 2022
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER: ________________________________
CONTRACTOR: See Attached COR#7
ENGINEER: ________________________________