Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # E-6
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: September 9, 2026
AGENDA ITEM: Approval of Pay Application #16 – Miron Construction – Tiffin Recreation
Center
ACTION: Motion
Background
The City of Tiffin entered into a construction agreement with Miron Construction Co., Inc. for
the construction of the Tiffin Community Recreation Center at 105 S. Park Road. The original
contract amount was $12,435,142.00, with the contract dated November 19, 2024.
Pay Application No. 16 reflects $435,269.69 in work completed during the current billing period.
Total completed and stored work to date is $9,426,010.65, representing approximately 83% of
the current contract amount.
The current contract amount has been adjusted through previously approved change orders. The
original contract amount of $12,435,142.00 has a net change of -$1,042,001.88, resulting in a
current contract amount of $11,393,140.12. No new change orders are included in Pay
Application No. 16.
The detailed continuation sheets indicate that major portions of the building are substantially
complete, including metal building systems, elevators, masonry, site utilities, aggregate piers,
and several other building systems. Remaining work includes items such as flooring, HVAC,
electrical, landscaping, asphalt paving, concrete site work, and other site and finish work.
Recommendation
Staff recommends that the City Council approve Pay Application No. 16 from Miron
Construction Co., Inc. in the amount of $413,506.21 for the Tiffin Community Recreation Center
project.
ATTACHMENTS: Pay Application
1
Sources
- revize: E-6 (1G1TO2FVx6xz7TAbGoQEW3hRovcHkR.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-6 Approval of Pay Application #16 – Miron Construction – Tiffin Recreation Facility
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.