City Engineer's Report — L-1
Page 1 of 5
Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISON:
Andrew Inhelder, PE
Office: 319.364.4773
Cell: 515.802.0906
[email protected]
DATE:
October 1, 2026
ON-GOING PROJECTS
REVERSE OSMOSIS WATER TREATMENT PLANT DESIGN – CLINT WIENEN
The RO skids have been delivered and assembled. Driveway paving has been partially completed. Metal
roofing has been installed on the RO building. Trusses and metal roofing have been installed for the
addition onto the existing building. Roofers are expected to be completed within the next month. Both
north and south mezzanine have been framed. The new high service pump has been placed into the
pumphouse. Work to be completed in the next month includes metal siding and roofing, truss installation
on the addition to the existing treatment building, finish mezzanine and stair construction, pave trail and
entrance, and ongoing electrical, plumbing, HVAC, and process piping items.
At the construction meeting held on 9/29/2026, Tricon Construction is not anticipating the RO System to
be operational until mid to late November. Substantial Completion was identified as 9/30/2026 in the
Agreement.
WELL 6 – CLINT WIENEN
The City signed the PSA presented at the September 15th council meeting.
HIGHWAY 6 CONCEPT AND COST ESTIMATE – JAMES WATTERS
Final plans for letting were submitted to the DOT on August 4, 2026. The project is currently out for
bidding and MSA is answering Contractor questions. The DOT will open bids on October 20, 2026.
The DOT is currently working on the construction agreement with the City and will be submitting to the
City for signature when ready. This agreement will put in place construct cost splits between the City and
DOT.
PROJECT UPDATE
Page 1 of 5
Sources
- revize: L-1 (xNebE2ZWEHhrQVFZn4K83NjMCqBM7z.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-1 City Engineer's Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.