contract agreement · K-3
K-3 - Change Order #17 – Rathje Construction, Original Town Urbanization Phase Two
Page 1 of 4
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 15 July, 2022
Change Order No: 17 (seventeen)
Agreement Date: 5 May, 2020
PROJECT: Original Town Urbanization Project: Phase Two HFC#12218.13123
OWNER: City of Tiffin, IA
CONTRACTOR: Rathje Construction
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
This change order includes relocation of a fire hydrant, installation of new mailboxes per homeowner requests, relocation of a water service line, additional pavement sawing and grading, and replacement and relocation of a damaged street light handhole that was installed Phase 1. Due to a holiday, 7 additional day pushes the completion date to September 9, 2022
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $1,824,618.96
CONTRACT with LAST CHANGE ORDER: $1,958,804.08
THIS CHANGE ORDER AMOUNT: $16,783.50
NEW CONTRACT PRICE: $1,975,587.58
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): 7 days - rain days
NEW Completion Date: September 9, 2022
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER: ________________________________
CONTRACTOR: See Attached COR#19
ENGINEER: ________________________________