Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISONS:
Andrew Inhelder, PE
Office: 319.364.4773
Cell(s): 515.802.0906
[email protected]
DATE:
September 27, 2023
ON-GOING PROJECTS
North Park Road Improvements – James Watters
MSA received a response from the IaDOT regarding the application to the Traffic Safety Improvement Program
(TSIP). The DOT’s opinion is that the program is to fund projects with existing traffic/safety issues rather than
projects trying to mitigate future problems. With this understanding the DOT concluded this project would not
be a suitable candidate for TSIP funding.
MSA is inquiring with DOT personnel on applicability of project for Statewide Transportation Alternative
Program (TAP) funding.
MSA is preparing an application to the Iowa Clean Air Attainment Program (ICAAP) funding for submittal by
Oct 1, 2023.
MSA has received direction from the City to proceed with one roundabout at the second entrance north of the
USH 6 roundabout on Park Rd. School district is no longer interesting in funding a second roundabout at the
entrance to Oak Hill Elementary.
Highway 6 Concept and Cost Estimate – Ben Wilkinson
MSA has completed our conceptual design of the project and finalized the draft cost estimate and cost sharing
estimate. MSA forwarded that to City for review and then a follow up with the DOT will be scheduled. MSA is
still waiting on the DOT to determine recommendations on the two structures.
Comprehensive Water System Evaluation – Clint Wienen
The RO pilot has been completed. We are currently working on finalizing cost estimates for (3) building options
(masonry, precast concrete, and pre-engineered steel). Once the estimates are completed, we will present to
the council for a decision. We are also waiting for the pilot study report to be finalized by Harn.
Trail Connection between Roundabout and Parking Lot – Andrew Inhelder
Plans are being internally reviewed for QAQC. Once plans have been reviewed a final plan set will be sent to
the City for review/comment and plans will be sent for bidding.
PROJECT UPDATE
Page 1 of 3