WS - C - Water Plant Project - Cost Estimate, Layout, Concept

Dated December 5, 2023City Council — work session, December 5, 2023 7 pages

Open the PDF Searchable (OCR) PDF

Page 1 of 7

Text read by the vision model; check the PDF for anything that matters.
TIFFIN WTP UPGRADES - COST ESTIMATE SUMMARY <table> <tr> <th></th> <th>WTP Upgrades with Steel Building</th> <th>WTP Upgrades with Precast Concrete</th> </tr> <tr> <td>Construction Costs</td> <td>$8,772,630</td> <td>$9,498,412</td> </tr> <tr> <td>Inflation</td> <td>$263,179</td> <td>$284,952</td> </tr> <tr> <td>Contingency</td> <td>$877,263</td> <td>$949,841</td> </tr> <tr> <td>Total Capital Cost</td> <td><b>$9,913,071</b></td> <td><b>$10,733,205</b></td> </tr> </table>