engineering report · M-8
M-8 - City Engineer Report
Page 1 of 4
Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISON:
Andrew Inhelder, PE
Office: 319.364.4773
Cell: 515.802.0906
[email protected]
DATE:
November 25, 2024
ON-GOING PROJECTS
North Park Road Improvements – James Watters
MSA received the IaDNR permit for watermain extension on 9/23/24
Private utilities plan to relocate this fall. Workplans for relocation have been reviewed.
MSA and City have met with Linn County REC to begin utility relocations. Linn County REC has sent
an invoice to City for relocation. Relocation is expected to begin in December 2024.
MSA met with representatives from South Slope to review relocation needs. South Slope has
materials on hand to relocate and can begin this fall/winter. MSA has reviewed the relocation plan
and South Slope presently intends to open-trench the majority of their line with 2 bore locations
where the line is required to be too deep for a trench. An updated invoice is expected to be
received by the City on or before the week of Thanksgiving.
MSA met with representatives from Segra (formerly UPN) to review relocation needs. Segra began
relocation work on 11/11/2024 and is expected to complete work in the next few weeks.
Easements for the project were secured and Project Development Certification Form will be submitted to
Iowa DOT Local Systems Bureau by Nov 1 so project can proceed to letting.
Project is scheduled for a Bid Letting date of Dec 17, 2024.
MSA is reviewing Construction Administration requirements and expects to submit a cost estimate and
contract for these services for the North Park Rd project in 2025. to the City in December.
Highway 6 Concept and Cost Estimate – James Watters
All utilities have returned a signed acknowledgement of the project. Utility Impact exhibits will be
distributed in Winter 2024/2025 to utilities. The Utility Coordination Meeting is TBD.
MSA/City are awaiting final PreDesign agreement from DOT for project.
MSA revised current D5 (Plans to Right of Way) plan set and estimate and resubmitted to DOT on
11/22/2024. Right of way acquisition will begin in 2025 for the project.
PROJECT UPDATE