K-2 - Change Order 3 - Boomerang - Potter Creek Sewer Interceptor
Page 1 of 2
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 6/18/2024
Change Order No: 3 (THREE)
Agreement Date: 7/6/2023
PROJECT: Potter Creek Interceptor Sewer Project #21218.244
OWNER: Tiffin, IA
CONTRACTOR: Boomerang Corp
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Deduction from retainage for repair of street. See attached RFC#5.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $1,067,837.60
CONTRACT with LAST CHANGE ORDER: $1,079,277.40
THIS CHANGE ORDER AMOUNT: $(3,000.00)
NEW CONTRACT PRICE: $1,076,377.60
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): N/A
NEW Completion Date: N/A
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER:
CONTRACTOR: See Attachment for signature.
ENGINEER: