Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISONS:
Kevin Bailey, PE / Jake Huck, P.E.
Office: 319.364.4773
Cell(s): 319.855.8392/ 563.542.6571
[email protected] / [email protected]
DATE:
September 30, 2022
ENGINEERING SERVICES
Upcoming Projects
A summary of major upcoming infrastructure projects is listed below.
Major Upcoming Description Next Steps/Schedule
Infrastructure Project
Wastewater Treatment The current wastewater treatment facility (WWTF) has a Final Compliance with NPDES
Improvements chloride compliance schedule. There is not any wastewater Permit required October 1, 2025.
treatment equipment/processes designed to remove chloride
so typically source control is the only economical means of MSA and City staff met to
meeting compliance. The existing treatment facility is at about discuss the findings. MSA has
50% capacity. However, if the past growth rate continues an prepared a proposed schedule
expansion will be required in the next 6-8 years. for wastewater treatment, water
treatment and water supply
improvement projects.
Water System Scope includes additional capacity (wells and water treatment
Improvements plant expansion) and new water tower. It is our understanding
that a new well is the process of being drilled. However, the MSA and City staff met to
existing treatment plant only has capacity to treat the existing discuss the findings. MSA has
wells and the new well will provide redundancy should one of prepared a proposed schedule
the existing wells be out of service. We are evaluating for water treatment, wastewater
treatment process that would be capable of eliminating treatment and water supply
chlorides to achieve compliance with the future chloride limit at improvement projects.
the WWTF. Future expansion will also likely be required if the
past growth rate continues (similar to the WWTF).
Park Road Improvements We understand this is a high priority project with the City to Design 2023/Construction 2024
relieve congestion on the old 2-lane section of roadway. MSA
remains available for planning and design of the final phase of
Park Road from near Aster Drive to Hwy 6 when funding
becomes available.
Highway 6 - City of Tiffin Scope is to develop a concept and cost estimate for Highway 6 MSA submitted preliminary
Park Road roundabout to from 900’ west of the roundabout at Park Road west to Main concepts to the IowaDOT. Upon
Main Street improvements Street. The concept and cost estimate will be used to determine receipt of the IowaDOT’s review
type of IowaDOT project and potential funding for construction. comments, MSA will make
necessary revisions and prepare
an estimate of construction cost.
PROJECT UPDATE
Page 1 of 2