Discussion and Consideration of Pay Application #5 – Miron Construction, Recreation Center - Motion to Approve
Page 1 of 5
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-5
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: October 3, 2025
AGENDA ITEM: Discussion and Consideration of Pay Application #5 – Miron Construction,
Recreation Center
ACTION: Approval
Purpose
To request Council approval of Pay Application #5 from Miron Construction Co., Inc. for work
completed on the Tiffin Recreation Center project.
Background
Miron Construction is the general contractor for the Tiffin Recreation Center project. The
original contract amount was $12,435,142.00. A change order approved on September 25, 2025
reduced the contract by $1,042,001.88, resulting in a revised contract total of $11,393,140.12.
Pay Application #5 covers the period ending September 30, 2025, and includes:
• Total completed and stored to date: $749,806.93
• Retainage (5%): $37,490.35
• Total earned less retainage: $712,316.58
• Less previous payments: $519,083.09
• Current payment due: $193,233.49
• Balance to finish, including retainage: $10,680,823.54
This application has been reviewed and certified by Atura Architecture, the project architect, and
is recommended for approval.
Recommendation
Staff recommends approval of Pay Application #5 in the amount of $193,233.49 to Miron
Construction Co., Inc. for work completed on the Tiffin Recreation Center project.
ATTACHMENTS: Pay App
1
Sources
- revize: Attachment (Mc33ppdjJQ5OYq1y4HDGu7wu7gZmWS.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-5 - Staff Report - Pay App #5 - Miron Construction - Tiffin Recreation Center.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Discussion and Consideration of Pay Application #5 – Miron Construction, Recreation...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.