Discussion and Consideration of Pay Application #6 – Miron Construction, Recreation Center – Motion to Approve
Page 1 of 5
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-5
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: October 31, 2025
AGENDA ITEM: Discussion and Consideration of Pay Application #6 – Miron Construction,
Recreation Center
ACTION: Approval
Overview
This report is submitted for Council consideration of Pay Application #6 from Miron
Construction Co., Inc. for work completed on the City of Tiffin Community Recreation Center
located at 105 S Park Road.
Pay Application #6 Details
• Application Period: Through October 31, 2025
• Total Completed & Stored to Date: $2,417,411.86
• Retainage: $120,870.60
• Total Earned Less Retainage: $2,296,541.26
• Less Previous Payments: $712,316.58
• Current Payment Due: $1,584,224.68
• Balance to Finish (Including Retainage): $9,096,598.86
Scope of Work Included
This pay application covers progress on:
• General conditions and requirements
• Construction fee and preconstruction services
• Cast-in-place concrete
• Steel fabrication and erection
• Electrical work
• Earthwork and site utilities
• Landscaping and allowances
Recommendation
Based on the architect’s certification and staff review, staff recommends approval of Pay
Application #6 in the amount of $1,584,224.68 to Miron Construction Co., Inc. for work
completed on the Community Recreation Center project.
ATTACHMENTS: Pay Application
1
Sources
- revize: Attachment (deBcfgZdwqqD4F1E9JWVcEmOcoBS0A.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-5 - Pay Application #6 – Miron Construction, Recreation Center.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Discussion and Consideration of Pay Application #6 – Miron Construction, Recreation...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.