Discussion and Consideration of Pay Application #2 – Cornerstone Excavating, Inc. – Earth Stockpile Spreading Project – Motion to Approve
Page 1 of 3
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-4
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: November 24, 2025
AGENDA ITEM: Discussion and Consideration of Pay Application #2 Cornerstone
Excavating, Inc. – Earth Stockpile Spread Project
ACTION: Approval
Background
The City of Tiffin entered into a contract with Cornerstone Excavating, Inc. for the Earth
Stockpile Spread project. The original contract amount was $138,050.00. Approved change
orders have increased the contract sum by $14,825.25, bringing the total contract amount to
$152,875.25.
• Total completed and stored to date: $151,652.75
• Retainage (3%): $4,549.58
• Total earned less retainage: $147,103.17
• Less previous payments: $141,283.17
• Current payment due: $5,820.00
• Balance to finish (including retainage): $5,772.08
The work has been verified by the Construction Manager and Architect as being in accordance
with contract documents.
Recommendation
City Engineer recommends approval of Pay Application #2 in the amount of $5,820.00 to
Cornerstone Excavating, Inc.
ATTACHMENTS: Pay Application
1
Sources
- revize: Attachment (XYPmeq7ih5XjwUu4Bo3y1GfJGpyazp.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (K-4 - Pay Application #2 - Cornerstone Excavating - Earth Stockpile Spreading.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Pay Application #2 – Cornerstone Excavating, Inc. –...