contract agreement · E-3
Approval of Pay Application #18 - Boomerang Corp - North Park Road Improvements Project — E-3
Page 1 of 21
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # E-3
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: October 29, 2026
AGENDA ITEM: Approval of Pay Application #18 – Boomerang Corporation – North Park
Road Improvement Project
ACTION: Motion
Background
The City of Tiffin is completing the North Park Road Improvements Project under contract with
Boomerang Corp. The project includes roadway improvements, storm sewer infrastructure, water
main improvements, pedestrian facilities, and related improvements.
Pay Application #18 covers work completed during the pay period of September 27, 2026,
through October 24, 2026.
The payment application identifies the following project financial information:
• Original Awarded Contract Amount: $5,458,891.91
• Authorized Contract Amount: $5,586,322.65
• Current Payment Request: $133,980.94
• Approved Work to Date: $5,270,279.60
• Payments to Date, Including This Application: $5,242,167.85
The payment application reflects no additional retainage, liquidated damages, or adjustments for
this pay period.
Recommendation
Staff recommends that the City Council approve Pay Application #18 for Boomerang Corp. in
the amount of $133,980.94 for the North Park Road Improvements Project.
ATTACHMENTS: Pay Application
1
Sources
- revize: E-3 (MaCntbwX5PaONVYXS5XSzbSIID9Ujc.pdf) — where it was found ↗ first seen Oct 30, 2026
Attached to agenda item: E-3 Approval of Pay Application #18 - Boomerang Corp - North Park Road Improvements Project
Data last updated October 30, 2026. Built from the archive's documents; see how the data is built.