Contract Summary Construction Manager Contingency Summary Owner Contingency Summary
Original Contract Amount: $12,435,142.00 CMaR Contingency Amount: $567,585.00 Owner Contingency Amount: $0.00
Change Orders to Date: $0.00 Change Orders to Date: -$154,781.41 Change Orders to Date: $225,451.17
Current Contract Value: $12,435,142.00 CMaR Contingency Value: $412,803.59 Owner Contingency Value: $225,451.17
Current Scope Revisions
CMaR Owner
Allowance Contingency Contingency Estimated Cost
Description Number Date Submitted Status Item? Item? Item? Impact
Project Contingency PCI's June 2025 thru November 2025 001-016 11/30/2025 Approved Yes -$49,275.08
Owner Contingency PCI's June 2025 thru November 2026 001-016 11/30/2025 Approved Yes -$125,040.83
RFI #14 Add additional data outlets for TV on elevator wall 017 12/2/2025 Approved Yes -$1,581.78
ASI-10 CMU Lintel Revision 018 12/8/2026 Approved Yes $0.00
ASI-11 Court Dimensions Revisions 019 1/5/2026 Approved Yes $0.00
Seehase Masonry - Broken Key, Drill and Epoxy, Hauling
Water 020 1/5/2026 Approved Yes -$695.00
ASI-13 Civil Revisions 021 3/3/2026 Collecting Pricing Yes -$4,874.53
ASI-12 Exterior Elevation Revised and Clarified 022 1/20/2026 Approved Yes $0.00
Add backing panel to exterior signage 024 2/17/2026 Approved Yes -$14,800.00
Change AF-2 from 20% fleck color to 30% fleck color 025 2/17/2026 Approved Yes -$2,061.20
Repair broken conduit 026 2/23/2026 Approved Yes -$801.62
RFI#23 2nd Floor Deck Endgine 027 3/4/2026 Approved Yes -$14,222.20
Remake Exterior Duct Work due to Steel Column Conflict 028 3/5/2026 Approved Yes -$2,160.00
Owner Progress Report | 250120 March 2026 Miron Construction Co., Inc. | 10
Sheets in this document
- p. 30 1 · Rezoning Exhibit · MMS Consultants
- p. 75 Title Sheet · MSA · G1 Project Overview
- p. 76 CP1 · Elevation · MSA · Roberts Ferry RD & Village DR Signal Improvements
- p. 77 Removal Plan · MSA · Roberts Ferry RD & Village DR Signal Improvements
- p. 78 Traffic Control Plan · MSA · Roberts Ferry RD & Village DR Signal Improvements
- p. 79 Pavement Marking Plan · MSA · Village DR
- p. 80 Point Number & Elevation · MSA
- p. 81 Curb Ramp Details · MSA · Roberts Ferry RD & Village DR Signal Improvements
- p. 113 City of Tiffin FY 25-26 Town Hours by Month (chart; data on p. 112)
- p. 116 City of Tiffin FY 25-26 (chart; data on p. 114)
Sources
- revize: Agenda packet (packet_2026-04-21_40d71ad9-b59e-4a3a-a8d6-2b69c659f62d.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 21, 2026. Built from the archive's documents; see how the data is built.