ON-GOING PROJECTS
REVERSE OSMOSIS WATER TREATMENT PLANT DESIGN – CLINT WIENEN
The precast walls and ceiling for the RO Building have been installed. Rough-Ins for the underground
plumbing and electrical are nearly complete below the RO Building floor slab. The roof trusses for the RO
Building have been installed, and the Contractor is continuing with sheathing. They plan to pour the RO
Building floor slab in the upcoming weeks. The base slab and wall pours have been completed for the
Clearwell. They are planning to have the Clearwell concrete completed by the end of the month. They are
also planning to pour the remaining footings and foundation walls for the existing water treatment plant
expansion in the next few weeks.
SYSTEMWIDE SANITARY SEWER MODEL – ERIC THOMPSON
MSA has integrated the Lift Station draw down results into the sanitary model and will be re-running the
model with the known development conditions. MSA is also reviewing potential future sites for regional
Lift Stations based on topography and potential service areas.
VILLAGE DRIVE & ROBERTS FERRY ROAD SIGNAL DESIGN – CHAD WAGNER
Project was awarded to Neumiller Electric, Inc on May 19th, 2026. Contractor is working on completing the
construction contract and has begun preparing shop drawings for review. A pre-construction meeting will
be scheduled for after the construction contract is approved.
PROJECT UPDATE
Page 1 of 5
Sources
- revize: L.1 (Yiz9KekkZfuN84KtexBpk9rR9zyvCO.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-1 City Engineer Report
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.