Discussion and Consideration of Pay Application #9 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.4
Page 1 of 12
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-4
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: May 29, 2026
AGENDA ITEM: Discussion and Consideration of Pay Application #9 – Tricon Construction –
Tiffin Water Treatment Facility Upgrade Project
ACTION: Motion
Background
Tricon Construction Group has submitted Pay Application No. 9 for work completed on the
Water Treatment Plant Upgrades Project through May 20, 2026. The application has been
reviewed by the City's engineering consultant, MSA Professional Services, and reflects
construction activities completed during the current pay period.
The Water Treatment Plant Upgrades Project remains one of the City's largest infrastructure
investments and is critical to supporting Tiffin's continued growth, system reliability, and long-
term water capacity needs. Construction activities continue on multiple components of the
project, including treatment process facilities, site improvements, electrical systems, piping, and
structural work.
Recommendation
Staff and MSA Professional Services recommend approval of Pay Application No. 9 submitted
by Tricon Construction Group in the amount of $904,401.14. The work associated with this
payment request has been reviewed and is consistent with project progress achieved during the
current billing period.
ATTACHMENTS: Pay Application
1
Sources
- revize: K.4 (Ntl5mzJhqkwJMVTuAH5usiSMadPymK.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Pay Application #9 – Tricon Construction – Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.