contract agreement · K-2
Discussion and Consideration of Change Order #16 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.2
Page 1 of 5
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-2
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: May 29, 2026
AGENDA ITEM: Discussion and Consideration of Change Order #16 – Boomerang
Corporation – North Park Road Improvements Project
ACTION: Motion
Background
Boomerang Corp. and MSA Professional Services have submitted Change Order No. 16 for the
North Park Road Extension Project. The change order addresses work associated with storm
sewer improvements that was included within the project plans but inadvertently omitted from
the original bid schedule.
Specifically, the change order adds three connections to an existing 30-inch reinforced concrete
storm sewer pipe for intakes I-28 and I-29. Two connections are required at Intake I-29 and one
connection is required at Intake I-28. While removal and replacement of the existing storm sewer
pipe were included in the original contract, a pay item for the additional work necessary to
connect the new infrastructure to the existing storm sewer system was not included in the bid
documents.
Change Order No. 16 increases the contract amount by $7,500.00, resulting in a revised contract
amount of $5,561,949.41. The change order establishes a unit price of $2,500 per connection for
three storm sewer connections.
MSA Professional Services reviewed the proposed pricing and determined the negotiated unit
cost is reasonable based on a comparison with similar bid items from comparable projects. The
proposed unit price is above the average bid price but below the highest bid price identified
through the engineer's bid tab analysis.
There is no impact to the project schedule. The engineer has determined that the change order
does not affect the controlling items of work and no contract time adjustment is required.
Recommendation
Staff and MSA Professional Services recommend approval of Change Order No. 16 in the
amount of $7,500.00. The change order addresses necessary work required to complete the storm
sewer improvements and properly connect the new infrastructure to the existing system.
ATTACHMENTS: Change Order
1
Sources
- revize: K.2 (7Wi8X6S26cbSL6rfw8QgXAcmM4whut.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Change Order #16 – Boomerang Corporation – North Park...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.