Text from the PDF text layer; check the PDF for anything that matters.CHAPTER 170 SUBDIVISION REGULATIONS
necessary to service the subdivision itself. Other subdivisions which
connect with the systems shall on a prorata basis reimburse the City
for the cost of the additional system, which shall service that
subdivision and meet all City specifications.
(2) The City’s inability to efficiently collect or treat wastewater
may be grounds for rejection of a proposed subdivision. A
proportional fee may be requested by the City, from the subdivider, to
pay for the necessary upgrades in the sewer system.
(3) The sewer system improvements shall, upon inspection,
approval, and acceptance by the City, become the property of the
City.
(4) The subdivider must provide evidence of construction permits
from the Iowa Department of Natural Resources and other applicable
State and federal agencies prior to approval of the final plat.
C. Stormwater System. The subdivider of land being platted shall install
and construct a stormwater system adequate to serve the area, including
anticipated extension of use to serve additional areas. The Stormwater system
shall be constructed in compliance with Chapter 166.
(1) The stormwater drainage system shall be separated and
independent of any sanitary sewer system. The acceptable standard
for sizing storm sewers is to be a five-year, 24-hour storm event or as
specified under current design standards.
(2) Under some circumstances the City may require, as a
condition for approval of the plat, installation of a stormwater system
that is larger than necessary to meet the needs of the platted area, but
necessary to complete the City stormwater system as it relates to both
the area being platted and other areas. In such event, the City shall
pay on a prorata basis for the excess cost over that which is necessary
to service the subdivision itself. Other subdivisions which connect
with the systems shall on a prorata basis reimburse the City for the
cost of the additional system, which shall service that subdivision and
meet all City specifications.
(3) Stormwater facilities shall be located in the road right-of-way
where feasible, or in the perpetual unobstructed easements of
appropriate width.
(4) In the stormwater design phase, the subdivider shall study the
effect of each subdivision on existing downstream drainage facilities
outside the area of the subdivision. The subdivider’s drainage studies
together with such other studies as shall be appropriate shall serve as
a guide to needed improvements. Where it is anticipated that the
additional runoff incident to the development of the subdivision will
overload an existing downstream drainage facility, the Council may
withhold approval of the subdivision until provision has been made
for the recovery of the cost for the improvement of said potential
condition in such sum as the Council shall determine. No subdivision
shall be approved unless adequate drainage will be provided to an
adequate drainage watercourse or facility.
CODE OF ORDINANCES, TIFFIN, IOWA
- 1836 -
Sources
- revize: Tiffin City Code - DRAFT (gFbbE0YR86eHDItZtXhZZqxLfknUlz.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: C Discussion and Review of Tiffin Municipal Code Revisions – Preparation for Setting the...
Data last updated October 22, 2026. Built from the archive's documents; see how the data is built.