K-2 - Change Order 9 - Balancing CO - Rathje Construction - Roundabout Project
Page 1 of 4
Text from the PDF text layer; check the PDF for anything that matters. Accounting ID No.(5-digit number):35768
Form 831240 (12-20)
Change Order No.:9
CHANGE ORDER
For Local Public Agency Projects
No.: 9 Non-Substantial:
Substantial: Administering Office
Concurrence Date
Accounting ID No. (5-digit number):35768 Project Number: STP-A-006-7(90)--22-52
Contract Work Type: PCC Pavement - Grade & Replace Local Public Agency: City of Tiffin
Contractor: Rathje Construction Co. Date Prepared: January 20, 2022
You are hereby authorized to make the following changes to the contract documents.
A - Description of change to be made:
0090 - Decrease Item for PAVED SHOULDER, HOT MIX ASPHALT MIXTURE, 6 IN.
0100 - Increase Item for PAVED SHOULDER, HOT MIX ASPHALT MIXTURE, 8 IN.
0120 - Increase Item for PAVEMENT SCARIFICATION
0130 - Decrease item for STANDARD OR SLIP FORM PORTLAND CEMENT CONCRETE PAVEMENT, CLASS C, CLASS 3
DURABILITY, 10 IN.
0230 - Increase Item for DETOUR PAVEMENT
0240 - Increase Item for TEMPORARY PAVEMENT
8006 - Add Item for DISINCENTIVE FOR BUMPS/DIPS NOT CORRECTED
8007 - Add Item for (PRICE ADJUST) PCC TRANSVERSE GROOVE DEFICIENT
8008 - Add Item for PAYMENT ADJUSTMENT INCENTIVE/DISINCENTIVE FOR PCC PAVEMENT THICKNESS (BY
SCHEDULE)
8998 - (PRICE ADJUST) LIQUIDATED DAMAGES
B - Reason for change:
0090 - Item is being deleted from the Contract, see Item 0100
0100 - All shoulders were installed at 8-inch thickness and used as temporary traffic surface. The additional thickness allows for
better load support for traffic.
0120 - Due to conflicting subcontractor schedules, the contractor performed all scarification at the same time which required
additional scarification to produce a 'smooth' (no abrupt elevation changes) pavement surface.
0130 - Item reduced to reconcile under-run of contract quantity.
0230 - Error in estimated quantity for work associated with 2019 winter shutdown.
0240 - Error in estimated quantity for work associated with 2019 winter shutdown.
8006 - See Non-Compliance 003 for Smoothness. One dip was not corrected.
8007 - See Non-Compliance 003 for macrotexture. Areas of the pavement had excessive depth of macrotexture.
8008 - Core test results indicate incentive is warranted.
8998 - Contractor overran the number of days specified in the Contract.
C - Settlement for cost(s) of change as follows with items addressed in Sections F and/or G:
0090, 0100, 0120, 0130, 0230, 0240 Contract Unit Prices
8006-8008 - Unit price determined by schedule
8998 - Unit Price established by Contract
D - Justification for cost(s) (See I.M. 6.000, Attachment D, Chapter 2.36, for acceptable justification):
8006 - per Standard Specification 2316.05
8007 - per Construction Manual Chapter 2 Appendix 2-34(E). A 5% price adjustment is to be applied.
8008 - per Standard Specification 2301.05A
8998 - per Standard Specification 1108.08 and Page 2 of 4 of the Contract. The liquidated damages on the project do not exceed the
contract administration costs.