K-3 - Change Order 1 - Well 5 Pump, Controls, Watermain - Boomerang
Page 1 of 3
Text read by the vision model; check the PDF for anything that matters.February 2, 2023
CHANGE ORDER NO. 1
WELL 5 PUMP, CONTROLS AND WATER MAIN
TIFFIN, IOWA
Change Order No. 1 is for the following modifications to the project:
1. Upgrade of the Water Treatment Plant controls and telemetry per Automatic Systems. LS $7,320.80
2. Contractor's Markup LS $732.08
Total: $8,052.88
Change Order No. 1 increases the contract amount by $8,052.88.
BOOMERANG CORP.
By ________________________________
Title ______________________________
Date ______________________________
VEENSTRA & KIMM, INC.
By ________________________________
Title Project Engineer
Date February 2, 2023
CITY OF TIFFIN, IOWA
By ________________________________
Title ______________________________
Date ______________________________
ATTEST:
By ________________________________
Title ______________________________
Date ______________________________