Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISON:
Andrew Inhelder, PE
Office: 319.364.4773
Cell(s): 515.802.0906
[email protected]
DATE:
January 31, 2024
ON-GOING PROJECTS
North Park Road Improvements – James Watters
City received notice that it did not receive requested grant through the Iowa Clean Air Attainment Program.
MSA is awaiting notice of funding through State Wide Transportation Alternative Program (TAP). Anticipate
notice in spring 2024.
MSA resubmitted Concept Statement to Iowa DOT Local Systems Bureau on 1/8/24. The concept statement
was cleared by Local Systems Bureau on 1/9/24. MSA is awaiting environmental clearance from IaDOT NEPA
section based on updated information provided in concept statement.
MSA and City intend to meet the last week in January to go over the following items.
• Construction staging and traffic control
• Right-of-way
• Water main construction
• Environmental process
• Development adjacent to North Park Rd
Highway 6 Concept and Cost Estimate – James Watters
MSA survey crew has been on site to set control for project and collect initial data. Snow and cold
temperatures have delayed initial survey efforts. Survey staff intends to collect data of roadway and other
features that have been cleared of snow. Remaining data will need to be collected when weather permits,
and snow is melted.
Contract for design services will be submitted to City for approval in February.
Comprehensive Water System Evaluation – Clint Wienen
We are wrapping up the Preliminary Engineering Report (PER) and are planning to submit it to the DNR
within the next week.
Reverse Osmosis Water Treatment Plant Design – Clint Wienen
Survey of the site and soil borings have been completed. We are starting the preliminary design and will
schedule a meeting with City staff once the drawings are approximately 30% complete.
Trail Connection between Roundabout and Parking Lot – Andrew Inhelder
Project is constructed. Punchlist was created which will be completed in the spring 2024 for final
acceptance.
PROJECT UPDATE
Page 1 of 3