Text from the PDF text layer; check the PDF for anything that matters. ENGINEER'S OPINION OF PROBABLE COSTS
WELLNESS & RECREATION CENTER PHASE 2
PARKING LOT EXTENSION
TIFFIN, IOWA
DATE: 7/23/2024 Estimate Year 2024
MSA PROJECT #: 13603011 Construction Year 2025
Project Total
ITEM NO. SUDAS NO. DESCRIPTION UNIT UNIT PRICE QUANTITY TOTAL PRICE
Division 2: Earthwork
2.01 2010-C Clearing and Grubbing LS $ 2,000 1 $ 2,000
2.02 2040-D-1 Topsoil, On-site CY $ 10 1,400 $ 14,000
2.03 2010-E Excavation, Class 10 CY $ 10 1,400 $ 14,000
2.04 2010-G Subgrade Preparation, 12 in. Thickness SY $ 5 4,040 $ 20,200
2.05 2010-J Subbase, Modified, 4 in. Thickness SY $ 10 4,040 $ 40,400
2.06 2010-M Compaction Testing, Moisture & Density Control LS $ 3,000 1 $ 3,000
Division 7: Streets and Related Work
7.01 7010-A Pavement, PCC, 6 in. Thickness SY $ 50 3,800 $ 190,000
7.02 7010-I PCC Pavement Samples and Testing LS $ 4,000 1 $ 4,000
7.03 7030-A-1 Removal of Sidewalk SY $ 12 55 $ 660
Division 8: Traffic Control
8.01 8020-B Painted Pavement Markings, Waterborne STA $ 100 23.0 $ 2,300
8.02 8020-G Painted Symbols and Legends, Waterborne EA $ 125 6 $ 750
8.03 8030-A Temporary Traffic Control LS $ 2,000 1 $ 2,000
Division 9: Site Work and Landscaping
9.01 9010-B Hydraulic Seeding, Seeding, Fertilizing, and Mulching (BFM), Type 1 AC $ 4,000 0.4 $ 1,600
9.02 9040-A-1 Stormwater Pollution Prevention Plan (SWPPP) Preparation LS $ 2,500 1 $ 2,500
9.03 9040-A-2 Stormwater Pollution Prevention Plan (SWPPP) Management LS $ 3,300 1 $ 3,300
9.04 9040-F-1 Wattle, Installation LF $ 4 1,200 $ 4,800
9.05 9040-F-2 Wattle, Removal LF $ 1 1,200 $ 1,200
9.06 9040-Q-1 Erosion Control Mulching, Hydromulching (BFM) AC $ 2,000 0.8 $ 1,600
Division 11: Miscellaneous
11.01 11,020-A Mobilization LS $ 34,800 1 $ 34,800
11.02 11,050-A Concrete Washout LS $ 1,500 1 $ 1,500
ESTIMATED CONSTRUCTION SUBTOTAL $ 344,610
Contingency 20% $ 69,000
Inflation 5% per year $ 20,700
ESTIMATED CONSTRUCTION COST (2025) $ 434,310
Estimated Grant/Loan Administration $ -
Estimated Legal Fees 1% $ 4,400
Estimated Property Acquisition $ -
Estimated Design Engineering 10% $ 43,500
Estimated Construction Engineering 10% $ 43,500
TOTAL ESTIMATED PROJECT COST: $ 530,000
Disclaimers & Assumptions
This opinion of probable cost is approximate. Actual construction bids may vary significantly from this opinion due to timing of bids, constructual schedule restraints, labor rate
1
increases, material increases, or other factors beyond the control of the engineer.
2 Easements are estimations only. Compensation will be adjusted as needed during negotiations.
3 No lighting or private utility relocation costs included.
4 Assumes removal of existing structure as part of a separate contract, completed prior to this project.
5 Assumes surface drainage with grading to the north. No storm sewer or pipe culverts associated.
6 Assumes striping of new pavement only, no restriping of existing parking lot.
7 Assumes six (6) handicapped stalls with symbols.
G:\13\13603\13603011\_City Rec Center\Cost Estimates\13603011 OPC-Preliminary_2024-0719.xlsm Completed By:
Sources
- sharepoint (WS - D - Conceptual Parking Lot Expansion - Jim Bartels City Park.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.