engineering report · M-9
M-9 - City Engineer Report
Page 1 of 4
Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISON:
Andrew Inhelder, PE
Office: 319.364.4773
Cell: 515.802.0906
[email protected]
DATE:
August 29, 2024
ON-GOING PROJECTS
North Park Road Improvements – James Watters
Public involvement meeting was held at Tiffin City Hall on 6/25/24. Comments and feedback received at
the meeting where generally in support of the project and many attendees were interested in staging of
the project. Project is anticipated to be constructed over two construction years with final closeout
anticipated in 2027.
Army Corp of Engineers Permit has been submitted for the project on 6/18/24. Army Corp is requesting
purchase agreements for wetland and streambank credits. Purchase of these credits from area wetland and
stream credit banks is required to mitigate impacts to the stream crossing of N Park Rd, south of Mopar
Drive, which is considered a Waters of the United States (WOTUS) and is federally regulated. MSA has
contacted area wetland and stream credit banks and will forward cost and purchase agreements to the City
when ready.
MSA has submitted the IaDNR permit for watermain extension. MSA is discussing with private utilities for
relocations as needed. UPN plans to complete their relocation this fall.
MSA is working on final plans, specifications, and estimate for the project. These documents were
submitted to the IaDOT Local Systems Bureau for review. Final plans submitted for letting will occur on
September 17, 2024.
PROJECT UPDATE
Page 1 of 4